NPRR #491 · Revision Request
NPRR491 Updated Demand Response Information for ERCOT (formerly "Updated Distributed Generation and Demand Response Information for ERCOT")
ReasonPresently, the market (and possibly ERCOT) has extremely limited information on the MW capability and location of demand response Resources. Given that existing infrastructure, ERCOT situational awareness, Resource commitment and Locational Marginal Prices (LMPs) can be affected by demand response, this is a gap that needs to be addressed through enhanced reporting. Additionally, ERCOT would benefit from more granular information reported through a standard process to use in Load forecasting and commitment algorithms as well as the Report on the Capacity, Demand, and Reserves in the ERCOT Region and other short and long term analyses.
Created2012-11-15
Approved2013-07-16
Sections Affected
1.3.1.12.13.10.7.2.1 (new)3.14.3.4
Summary
This Nodal Protocol Revision Request (NPRR) proposes to provide ERCOT and the market with needed information on demand response.
Action Log 5 milestones
-
Nov 15
PRSDeferred/Tabled→ PRS Consideration
-
Apr 18
PRSRecommended for Approval→ PRS IA Review
-
May 16
PRSRecommended for Approval→ TAC Consideration
-
Jun 6
TACRecommended for Approval→ ERCOT Board Consideration
-
Jul 16
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Apr 18 '13 | PRS | To recommend approval of NPRR491 as amended by the 4/17/13 Edison Mission comments | Passed |
| May 16 '13 | PRS | To endorse and forward the 4/18/13 PRS Report as amended by the 5/9/13 ERCOT comments and Impact Analysis for NPRR491 to TAC with a recommended priority of 2013 and rank of 875 | Passed |
Documents 14
| Name | Type | Posted | Classification |
|---|---|---|---|
| 491NPRR-01 Updated Distributed Generation and Demand Response In | doc | Oct 19 '12 | Revision Request |
| 491NPRR-02 ERCOT Comments 103112 | doc | Oct 31 '12 | Revision Request Comments |
| 491NPRR-03 TIEC Comments 110712 | doc | Nov 7 '12 | Revision Request Comments |
| 491NPRR-04 PRS Report 111512 | doc | Nov 20 '12 | Committee Report |
| 491NPRR-05 WMS Comments 021513 | doc | Feb 15 '13 | Revision Request Comments |
| 491NPRR-06 Edison Mission Comments 021913 | doc | Feb 19 '13 | Revision Request Comments |
| 491NPRR-07 WMS Comments 041613 | doc | Apr 16 '13 | Revision Request Comments |
| 491NPRR-08 Edison Mission Comments 041713 | doc | Apr 17 '13 | Revision Request Comments |
| 491NPRR-09 PRS Report 041813 | doc | Apr 23 '13 | Committee Report |
| 491NPRR-10 ERCOT Comments 050913 | doc | May 9 '13 | Revision Request Comments |
| 491NPRR-11 Impact Analysis 051313 | doc | May 13 '13 | Staff Report |
| 491NPRR-12 PRS Report 051613 | doc | May 20 '13 | Committee Report |
| 491NPRR-13 TAC Report 060613 | doc | Jun 9 '13 | Committee Report |
| 491NPRR-14 Board Report 071613 | doc | Jul 17 '13 | Committee Report |
Meetings That Took It Up 22