NPRR #466 · Revision Request

NPRR466  Asset Depreciation Schedule for Capital Contributions

Approved sponsor RCWG posted 2012-05-24 ercot.com
ReasonAs part of its approval of NPRR432, Deployment of Resources to Alleviate Anticipated Emergency Conditions, the ERCOT Board directed TAC to develop an appropriate asset depreciation schedule that would apply to the capital contribution repayment obligation for Resources contracted to provide capacity pursuant to Section 6.5.1.1 that subsequently decide to re-enter the market.
Created2012-06-21
Approved2012-12-11
Sections Affected
6.5.1.1
Summary
This Nodal Protocol Revision Request (NPRR) creates an appropriate asset depreciation schedule to apply to the capital contribution repayment obligation for Resources contracted to provide capacity pursuant to Section 6.5.1.1.
Action Log 6 milestones
Amendments
DateBodyMotionResult
Jun 21 '12PRS To recommend approval of NPRR466 as revised by PRS.Passed
Jul 19 '12PRS To endorse and forward the 6/21/12 PRS Report as amended by the 7/3/12 ERCOT comments and Impact Analysis for NPRR466 to TAC.Passed
Sep 7 '12TAC To recommend approval of NPRR466 as recommended by PRS in the 7/19/12 PRS Report and as revised by TAC.Passed
Nov 29 '12TAC to recommend approval of NPRR466 as amended by the 11/26/12 ERCOT comments.Passed
Documents 11
NameTypePostedClassification
466NPRR-01 Asset Depreciation Schedule for Capital Contributions doc May 24 '12 Revision Request
466NPRR-02 WMS Comments 061412 doc Jun 14 '12 Revision Request Comments
466NPRR-03 PRS Report 062112 doc Jun 22 '12 Committee Report
466NPRR-04 ERCOT Comments 070312 doc Jul 3 '12 Revision Request Comments
466NPRR-05 Impact Analysis 071212 doc Jul 12 '12 Staff Report
466NPRR-06 PRS Report 071912 doc Jul 20 '12 Committee Report
466NPRR-07 TAC Report 090712 doc Sep 10 '12 Committee Report
466NPRR-08 Board Report 111312 doc Nov 14 '12 Committee Report
466NPRR-09 ERCOT Comments 112612 doc Nov 26 '12 Revision Request Comments
466NPRR-10 TAC Report 112912 doc Nov 30 '12 Committee Report
466NPRR-11 Board Report 121112 doc Dec 11 '12 Committee Report
Meetings That Took It Up 8
DateMeetingCommitteeStatus
Dec 11 '12 Board of Directors Meeting BOARD Concluded
Nov 29 '12 Technical Advisory Committee (TAC) Meeting TAC Concluded
Nov 13 '12 Board of Directors Meeting BOARD Concluded
Sep 7 '12 Technical Advisory Committee (TAC) Meeting TAC Concluded
Jul 19 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Jun 27 '12 Joint Credit Working Group (CWG)/Market Credit Working Group (MCWG) Meeting MCWG Concluded
Jun 21 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Jun 13 '12 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded