NPRR #443 · Revision Request
NPRR443 Removal of Switchable Generation Resource Plans from Protected Information
ReasonBecause the unavailability plans of Switchable Generation Resources are considered Protected Information, ERCOT cannot use this information in the Annual Planning Model or Five-Year Transmission Plan base cases, which are posted for Market Participant use. This could lead to reliability problems if the system is planned assuming that these Resources are available when, in fact, they are not. This could also lead to planning upgrades to resolve congestion caused by these Resources when the congestion will not occur because the Resource does not plan to be generating in ERCOT.
Created2012-02-23
Approved2012-07-17
Sections Affected
1.3.1.116.5.4
Summary
This Nodal Protocol Revision Request (NPRR) will remove the unavailability plans for Switchable Generation from the list of items considered to be Protected Information under the Protocols. This information will be reflected in the Annual Planning Models.
Action Log 5 milestones
-
Feb 23
PRSDeferred/Tabled→ PRS consideration
-
Apr 19
PRSRecommended for Approval→ PRS review the IA
-
May 17
PRSRecommended for Approval→ TAC consideration
-
Jun 7
TACRecommended for Approval→ Board consideration
-
Jul 17
BOARDApproved
Documents 11
| Name | Type | Posted | Classification |
|---|---|---|---|
| 443NPRR-01 Removal of Switchable Generation Resource Plans from | doc | Feb 7 '12 | Revision Request |
| 443NPRR-02 Impact Analysis 020712 | doc | Feb 7 '12 | Staff Report |
| 443NPRR-03 PRS Report 022312 | doc | Feb 27 '12 | Committee Report |
| 443NPRR-04 WMS Comments 031212 | doc | Mar 12 '12 | Revision Request Comments |
| 443NPRR-05 ROS Comments 031312 | doc | Mar 13 '12 | Revision Request Comments |
| 443NPRR-06 PLWG Comments 040412 | doc | Apr 4 '12 | Revision Request Comments |
| 443NPRR-07 ROS Comments 041612 | doc | Apr 16 '12 | Revision Request Comments |
| 443NPRR-08 PRS Report 041912 | doc | Apr 20 '12 | Committee Report |
| 443NPRR-09 PRS Report 051712 | doc | May 21 '12 | Committee Report |
| 443NPRR-10 TAC Report 060712 | doc | Jun 7 '12 | Committee Report |
| 443NPRR-11 Board Report 071712 | doc | Jul 17 '12 | Committee Report |
Meetings That Took It Up 9
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jul 17 '12 | Board of Directors Meeting | BOARD | Concluded |
| Jun 7 '12 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| May 17 '12 | Protocol Revision Subcommittee (PRS) Meeting | PRS | Concluded |
| Apr 19 '12 | Protocol Revision Subcommittee (PRS) Meeting | PRS | Concluded |
| Apr 12 '12 | Reliability and Operations Subcommittee (ROS) Meeting | ROS | Concluded |
| Mar 22 '12 | Protocol Revision Subcommittee (PRS) Meeting | PRS | Concluded |
| Mar 8 '12 | Reliability and Operations Subcommittee (ROS) Meeting | ROS | Concluded |
| Mar 7 '12 | Wholesale Market Subcommittee (WMS) Meeting | WMS | Concluded |
| Feb 23 '12 | Protocol Revision Subcommittee (PRS) Meeting | PRS | Concluded |