NPRR #440 · Revision Request
NPRR440 Consideration of Generation Availability in RMR Analyses
- PRS ✕ rejected Mar 22 '12
- TAC —
- BOARD —
- PUCT —
ReasonThe revisions proposed by this NPRR are necessary to ensure that sufficient Generation Resources are available in transmission-constrained areas to reliably manage constraints over at least a five year planning horizon.
Created2012-02-23
Rejected2012-03-22
Sections Affected
3.14.13.14.1.2
Summary
The Nodal Protocol Revision Request (NPRR) modifies provisions that relate to Reliability Must-Run (RMR) analysis to ensure generation availability is assessed by ERCOT in RMR evaluations over at least a five year planning horizon.
Timeline
-
Jan 30
PRSFiled by Paul Rocha on behalf of CenterPoint Energy
-
Feb 23
PRS Protocol Revision Subcommittee (PRS) MeetingPRSDeferred/Tabled Referred → ROS“To table NPRR440 and refer the issue to ROS.” — Passed→ PRS for consideration.
- Mar 7
-
Mar 8
Listed without action at 1 meeting
-
Mar 22
PRS Protocol Revision Subcommittee (PRS) MeetingPRSRejected Amended by the Feb 16 '12 Luminant Energy Company comments“To to recommend approval of NPRR440 as amended by the 2/16/12 Luminant Energy Company comments” — Failed
- Apr 5