NPRR #429 · Revision Request

NPRR429  HASL Offset Provision

Withdrawn sponsor Morgan Stanley posted 2011-11-22 ercot.com
ReasonCurrently the HASL calculation is performed by ERCOT and may require the Resource to operate in an undesirable range. The only current method of correcting this is to artificially move the High Sustained Limit (HSL) of the Resource down. The HSL change artificially limits the quantity of Responsive Reserve (RRS) the Resource can provide. This offset will allow the QSE to reflect an accurate HSL and still operate the Resource in a desirable range.
Created2011-12-15
Sections Affected
2.13.93.9.16.5.7.2
Summary
This Nodal Protocol Revision Request (NPRR) creates a High Ancillary Service Limit (HASL) Offset option that allows Qualified Scheduling Entities (QSEs) to move their HASL to a lower MW value if desired. The HASL Offset is added to other Ancillary Services being provided by the Resource to develop the HASL change.
Action Log 3 milestones
Documents 9
NameTypePostedClassification
429NPRR-01 HASL Offset Provision 112211 doc Nov 22 '11 Revision Request
429NPRR-02 PRS Report 121511 doc Dec 19 '11 Committee Report
429NPRR-03 ERCOT Comments 011312 doc Jan 13 '12 Revision Request Comments
429NPRR-04 PRS Report 011912 doc Jan 23 '12 Committee Report
429NPRR-05 ROS Comments 022012 doc Feb 20 '12 Revision Request Comments
429NPRR-06 ERCOT Comments 030712 doc Mar 7 '12 Revision Request Comments
429NPRR-07 ROS Comments 031312 doc Mar 13 '12 Revision Request Comments
429NPRR-08 PRS Report 032212 doc Mar 26 '12 Committee Report
429NPRR-09 Request for Withdrawal 100113 doc Oct 1 '13 Revision Request Comments
Meetings That Took It Up 38
DateMeetingCommitteeStatus
Oct 17 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Sep 19 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Aug 22 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Jul 18 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Jun 20 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
May 16 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Apr 18 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Mar 21 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Mar 13 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Feb 21 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Feb 13 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Jan 17 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Jan 9 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Dec 13 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Dec 5 '12 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Nov 15 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Nov 7 '12 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Oct 18 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Sep 20 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Aug 23 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Aug 15 '12 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Jul 19 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Jul 11 '12 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Jun 21 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Jun 14 '12 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Jun 13 '12 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
May 17 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
May 9 '12 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
May 4 '12 Qualified Scheduling Entity Managers Working Group (QMWG) Meeting QMWG Concluded
Apr 19 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Apr 11 '12 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Apr 9 '12 Qualified Scheduling Entity Managers Working Group (QMWG) Meeting QMWG Concluded
Mar 22 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Mar 8 '12 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Feb 23 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Feb 16 '12 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Jan 19 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Dec 15 '11 PRS Meeting PRS Concluded