NPRR #414 · Revision Request
NPRR414 UFE Calculation Clarifications
ReasonThis NPRR will provide clarification in the Protocols in regards to the utilization of Direct Current Tie (DC Tie) Schedules in the UFE calculations and remove "metered" from the UFE definition since non-metered Loads are also included in the UFE calculation.
Created2011-10-20
Approved2012-01-17
Sections Affected
2.111.4.611.4.6.1
Summary
This Nodal Protocol Revision Request (NPRR) clarifies language in the Unaccounted for Energy (UFE) calculation.
Action Log 4 milestones
-
Oct 20
PRSRecommended for Approval→ PRS review Impact Analysis
-
Nov 17
PRSRecommended for Approval→ TAC consideration
-
Dec 1
TACRecommended for Approval→ BOD consideration
-
Jan 17
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Oct 20 '11 | PRS | To recommend approval of NPRR414 as revised by PRS | Passed |
| Nov 17 '11 | PRS | To endorse and forward the 10/20/11 PRS Report as revised by PRS and Impact Analysis for NPRR414 to TAC. | Passed |
Documents 6
| Name | Type | Posted | Classification |
|---|---|---|---|
| 414NPRR-01 UFE Calculation Clarifications 091211 | doc | Sep 12 '11 | Revision Request |
| 414NPRR-02 Impact Analysis 091211 | doc | Sep 12 '11 | Staff Report |
| 414NPRR-03 PRS Report 102011 | doc | Oct 24 '11 | Committee Report |
| 414NPRR-04 PRS Report 111711 | doc | Nov 22 '11 | Committee Report |
| 414NPRR-05 TAC Report 120111 | doc | Dec 5 '11 | Committee Report |
| 414NPRR-06 Board Report 120111 | doc | Jan 17 '12 | Committee Report |
Meetings That Took It Up 4
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jan 17 '12 | Board of Directors Meeting | BOARD | Concluded |
| Dec 1 '11 | TAC Meeting | TAC | Concluded |
| Nov 17 '11 | PRS Meeting | PRS | Concluded |
| Oct 20 '11 | PRS Meeting | PRS | Concluded |