NPRR #405 · Revision Request
NPRR405 Clarification of DC Tie Load into Operational Systems and Processes
- PRS Nov 17 '11
- TAC Feb 2 '12
- BOARD Apr 17 '12
- PUCT —
ReasonThe Protocols are written to settle (charge) DC Tie exports as Load. However DC Tie exports are not being treated as Load from an operations perspective. DC Tie exports should receive the service that they pay for.
Created2011-10-20
Approved2012-04-17
Sections Affected
4.4.45.15.45.5.26.3.2
Summary
This Nodal Protocol Revision Request (NPRR) clarifies that Direct Current Tie (DC Tie) exports are to be treated as Load.
Timeline
-
Aug 29
PRSFiled by EDF Trading North America, LLC
- Sep 22
- Oct 11
-
Oct 12
Listed without action at 1 meeting
-
Oct 20
PRS PRS MeetingPRSRecommended for Approval“To recommend approval of NPRR405 as submitted.” — Passed→ PRS Impact Analysis review
-
Nov 17
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward the 10/20/11 PRS Report and Impact Analysis for NPRR405 to TAC.” — Passed→ TAC consideration of NPRR405
-
Dec 1
TAC TAC MeetingTACReferred Referred → WMS“To refer NPRR405 to WMS.” — Passed→ TAC consideration of NPRR405
- Dec 15
- Jan 6
-
Jan 11
WMS Wholesale Market Subcommittee (WMS) Meeting“WMS Motion to endorse NPRR405 with QMWG & ERCOT comments”“WMS Main motion to table NPRR405.”
-
Feb 2
TAC Technical Advisory Committee (TAC) MeetingTACRecommended for Approval Amended by the Jan 27 '12 CPS Energy comments“To recommend approval of NPRR405 as recommended by PRS in the 11/17/11 PRS Report, as amended by the 1/27/12 CPS Energy comments, and as revised by TAC.” — Passed→ ERCOT Board consideration of NPRR405
- Apr 16
-
Apr 17
BOARDEmail Vote / Unlisted MeetingBOARDApproved“To approve NPRR405 as recommended by TAC in the 2/2/12 TAC Report.” — Passed
-
—
Posted since the last meeting