NPRR #385 · Revision Request
NPRR385 Negative Price Floor (formerly "Security Violation Analysis and Reporting and Negative Price Floor")
- PRS Nov 15 '12
- TAC Nov 29 '12
- BOARD Dec 11 '12
- PUCT —
ReasonAs part of the holistic approach towards congestion irresolvable by Security-Constrained Economic Dispatch (SCED), the Congestion Irresolvable by SCED Task Force discussed the impact of Generation Resources on the other side of the constraints, in which ERCOT needs to back down. Those Generation Resources seem to be inequitably harmed as Real-Time Settlement Point Prices can drop to extremely negative values, which are unnecessary to send the proper price signal. This NPRR proposes an administrative price floor for Real-Time Settlement Point Prices of negative $251/MWh, consistent with the Energy Offer Curve offer floor described in Section 4.4.9.3.1, Energy Offer Curve Criteria, and the SCED over-generation power balance penalty curve of negative $251/MWh as established in the ERCOT Business Practice document "Setting the Shadow Price Caps and Power Balance Penalties in Security Constrained Economic Dispatch." The same negative $251/MWh price floor would also be applied to Day-Ahead Settlement Point Prices (DASPPs).
Created2011-07-21
Approved2012-12-11
Sections Affected
4.6.1.16.1.16.6.1.16.6.3.1
Summary
This Nodal Protocol Revision Request (NPRR) adds an administrative Settlement Point Price floor of negative $251/MWh.
Timeline
-
Jun 14
PRSFiled by Luminant Energy Company LLC
- Jul 13
-
Jul 21
PRS PRS MeetingPRSRecommended for Approval Amended by the Jun 21 '11 Luminant Energy Company LLC comments“To recommend approval of NPRR385 as amended by the 6/21/11 Luminant Energy Company LLC comments.” — Passed→ PRS Impact Analysis review
- Aug 5
-
Aug 18
PRS PRS MeetingPRSDeferred/Tabled“To table NPRR385 for one month.” — Passed→ PRS Impact Analysis review
- Sep 14
- Sep 15
- Sep 22
- Oct 11
- Oct 12
-
Oct 13
Listed without action at 1 meeting
- Oct 20
-
Nov 7
Listed without action at 1 meeting
- Nov 9
-
Nov 10
Listed without action at 1 meeting
- Nov 17
-
Dec 2
Listed without action at 2 meetings (Dec 2 '11 – Dec 7 '11)
- Dec 15
-
Jan 6
Listed without action at 4 meetings (Jan 6 '12 – Feb 8 '12)
-
Feb 15
WMS Wholesale Market Subcommittee (WMS) Meeting“WMS motion to endorse NPRR385 as revised by ERCOT comments and as amended by Lum comments.”
- Feb 23
-
Mar 7
Listed without action at 1 meeting
- Mar 22
-
Apr 11
Listed without action at 9 meetings (Apr 11 '12 – Jul 11 '12)
- Wholesale Market Subcommittee (WMS) Meeting
- Protocol Revision Subcommittee (PRS) Meeting
- Resource Cost Working Group (RCWG) Meeting
- Wholesale Market Subcommittee (WMS) Meeting
- Protocol Revision Subcommittee (PRS) Meeting
- Resource Cost Working Group (RCWG) Meeting
- Wholesale Market Subcommittee (WMS) Meeting
- Protocol Revision Subcommittee (PRS) Meeting
- Wholesale Market Subcommittee (WMS) Meeting
- Jul 19
-
Aug 15
Listed without action at 5 meetings (Aug 15 '12 – Oct 10 '12)
-
Oct 18
PRS Protocol Revision Subcommittee (PRS) MeetingPRSRecommended for Approval Amended by the Oct 16 '12 Luminant Energy Company LLC comments Remanded → PRS“To endorse the 7/21/11 PRS Report for NPRR385 as amended by the 10/16/12 Luminant Energy Company LLC comments and to request that NPRR385 return to the November 15, 2012 PRS meeting with an Impact Analysis.” — Passed→ PRS Impact Analysis review
-
Nov 15
PRS Protocol Revision Subcommittee (PRS) MeetingPRSRecommended for Approval Forwarded → TAC Amended by the Nov 14 '12 ERCOT comments priority 2013 · rank 367“To endorse and forward the 10/18/12 PRS Report as amended by the 11/14/12 ERCOT comments and Impact Analysis for NPRR385 to TAC with a recommended priority of 2013 and rank of 367.” — Passed→ TAC consideration of NPRR385
-
Nov 29
TAC Technical Advisory Committee (TAC) MeetingTACRecommended for Approval“To recommend approval of NPRR385 as recommended by PRS in the 11/15/12 PRS Report.” — Passed→ ERCOT Board consideration of NPRR385
-
Dec 11
BOARD Board of Directors MeetingBOARDApproved“To approve NPRR385 as recommended by TAC in the 11/29/12 TAC Report.” — Passed
-
—
Posted since the last meeting