NPRR #378 · Revision Request
NPRR378 Posting of the ERCOT Short-Term Load Forecast and the Aggregated HDL and LDL Used in SCED
- PRS withdrawn Dec 14 '11
- TAC —
- BOARD —
- PUCT —
ReasonThis NPRR will provide Market Participants the same data sets (subject to confidentiality provisions) that ERCOT uses within its Real-Time Market (RTM) systems for their use in making commercial and operational decisions and would support any long-term project ERCOT is currently evaluating an RTM upgrade project styled as Real-Time Market for Co-Optimizing Energy & Ancillary Services Combined with Demand Response. In the short term, to facilitate Market Participants’ decision making processes, this NPRR expands the Real-Time posting requirements on the MIS.
Created2011-06-23
Rejected2011-06-23
Sections Affected
6.5.7.5
Summary
This Nodal Protocol Revision Request (NPRR) adds a requirement for ERCOT to post on the Market Information System (MIS): (a) the ERCOT Short-Term Load Forecast (STLF) for the current Security-Constrained Economic Dispatch (SCED); (b) the STLF for the next or prompt five-minute SCED interval; and (c) the STLF effective within 15 minutes. This NPRR also clarifies SCED up/down reserves and adds capacity for the aggregate sum of the High Dispatch Limits (HDLs) and Low Dispatch Limits (LDLs) for the On-Line Generation Resources in each five-minute SCED interval.
Timeline
- Jun 8
- Jun 23
- Jul 7
-
Aug 4
TAC TAC MeetingTACRemanded Appeal Remanded → PRS“To grant the ERCOT Steel Mills appeal and remand NPRR378 to PRS; to direct PRS to work with ERCOT to resolve any questions needed to complete the Impact Analysis; to request that ERCOT perform an Impact Analysis; and to direct PRS to recommend action on NPRR378 to TAC after the completion of the Impact Analysis.” — Passed→ PRS consideration of NPRR378
- Aug 18
- Sep 22
-
Oct 20
Listed without action at 2 meetings (Oct 20 '11 – Nov 17 '11)
- Dec 14
-
Dec 15
Listed without action at 1 meeting