NPRR #375 · Revision Request
NPRR375 Extend the Reporting Horizon for CDR Inputs
- PRS Jul 21 '11
- TAC Aug 4 '11
- BOARD Sep 20 '11
- PUCT —
ReasonOn April 19, 2011, the ERCOT Board approved Planning Guide Revision Request (PGRR) 002, New Planning Guide Section 2, Definitions and Acronyms, and Section 8, Planning Reserve Margin (PRM) and Associated Change Process for the PRM (formerly "New Planning Guide Section 2, Definitions and Acronyms, and Section 8, Planning Reserve Margin") which requires the "Capacity, Demand and Reserves (CDR)" report to be produced for a ten year reporting horizon. ERCOT currently bases the calculation for years six through ten on the reported data for year five for Mothballed Generation Resource return-to-service probabilities, Private Use Networks and Switchable Generation Resources. This NPRR extends existing reporting requirements for these inputs to the CDR calculation to the full ten year horizon in order to provide more appropriate inputs to that calculation.
Created2011-06-23
Approved2011-09-20
Sections Affected
3.14.1.910.3.2.416.5.4
Summary
This Nodal Protocol Revision Request (NPRR) extends existing reporting requirements for Mothballed Generation Resource return-to-service probabilities, Generation Resources with associated Load, and Switchable Generation Resources, from five to ten years.
Timeline
- Jun 6
-
Jun 23
PRS PRS MeetingPRSRecommended for Approval“To recommend approval of NPRR375 as submitted” — Passed→ PRS IA Review
-
Jul 21
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward the 6/23/11 PRS Report and Impact Analysis for NPRR375 to TAC” — Passed→ TAC Consideration
-
Aug 4
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR375 as recommended by PRS in the 7/21/11 PRS Report” — Passed→ ERCOT Board Consideration
-
Sep 20
BOARD Board of Directors MeetingBOARDApproved Amended by the Sep 14 '11 ERCOT comments“To approve NPRR375 as amended by the 9/14/11 ERCOT comments” — Passed
-
—
Posted since the last meeting