NPRR #326 · Revision Request

NPRR326  Adjust the Calculation of the Real-Time Settlement Point Price for a Resource Node

Approved sponsor ERCOT posted 2011-02-10 ercot.com
ReasonThe current method of calculating payments and charges of Point-to-Point (PTP) Obligations and PTP Options settled in Real-Time based on Base Point weighted Real-Time Settlement Point Prices can lead to payments and charges when there is no congestion, which are not supported by congestion rent and can lead to Real-Time Revenue Neutrality Allocation uplift. With the implementation of this NPRR, payments and charges for PTP Obligations and PTP Options settled in Real-Time will be more accurate and should only occur when there is Real-Time congestion.
Created2011-03-24
Approved2011-06-21
Sections Affected
6.6.1.1
Summary
This Nodal Protocol Revision Request (NPRR) adjusts the calculation of the Real-Time Settlement Point Price for a Resource Node. The adjustment is to remove the Base Point weighting of the Real-Time Locational Marginal Prices (LMPs).
Action Log 4 milestones
Documents 11
NameTypePostedClassification
326NPRR-01 Adjust the Calculation of the Real Time Settlement Po doc Feb 10 '11 Revision Request
326NPRR-02 Impact Analysis 021011 doc Feb 10 '11 Staff Report
326NPRR-03 Reliant Energy Retail Services Comments 021111 doc Feb 11 '11 Revision Request Comments
326NPRR-04 Urgency Vote Ballot 021611 xls Feb 16 '11 Revision Request Ballot
326NPRR-05 Cost Benefit Analysis 031511 xls Mar 15 '11 Staff Report
326NPRR-06 PRS Report 032411 doc Mar 28 '11 Committee Report
326NPRR-07 Revised Cost Benefit Analysis 042011 xls Apr 20 '11 Staff Report
326NPRR-08 PRS Report 042111 doc Apr 26 '11 Committee Report
326NPRR-09 Revised Cost Benefit Analysis 042911 xls Apr 29 '11 Staff Report
326NPRR-10 TAC Report 050511 doc May 9 '11 Committee Report
326NPRR-11 Board Report 062111 doc Jun 22 '11 Committee Report
Meetings That Took It Up 5
DateMeetingCommitteeStatus
Jun 21 '11 Board of Directors Meeting BOARD Concluded
May 5 '11 TAC Meeting TAC Concluded
Apr 21 '11 PRS Meeting PRS Concluded
Mar 24 '11 PRS Meeting PRS Concluded
Feb 17 '11 PRS Meeting PRS Concluded