NPRR #310 · Revision Request
NPRR310 Expand Output Schedule Acceptable Range to Include HSL and LSL
- PRS Mar 24 '11
- TAC Apr 7 '11
- BOARD May 17 '11
- PUCT —
ReasonAllows for additional energy to be scheduled at the Resource limits. Reduces unnecessary validation notifications at the Resource limits.
Created2011-02-17
Approved2011-05-17
Sections Affected
6.4.2.3
Summary
This Nodal Protocol Revision Request (NPRR) updates the criteria by which Output Schedules are deemed valid to include Output Schedules that are equal in value to the Resource High Sustained Limit (HSL) and Low Sustained Limit (LSL).
Timeline
- Jan 14
-
Feb 17
PRS PRS MeetingPRSRecommended for Approval“To recommend approval of NPRR310 as submitted.” — Passed→ PRS review the IA.
- Feb 23
-
Mar 24
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC Priority“To endorse and forward the 2/17/11 PRS Report, Impact Analysis and Cost Benefit Analysis for NPRR310 to TAC with a recommended priority of High and a rank of 12.76.” — Passed→ TAC
- Apr 1
-
Apr 7
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR310 as recommended by PRS in the 3/24/11 PRS Report and the revised 4/6/11 Cost Benefit Analysis as revised by TAC.” — Passed→ BOD consideration
-
May 17
BOARD Board of Directors MeetingBOARDApproved“Approve NPRR310 as recommended by TAC in the 4/7/11 TAC Report.” — Passed
-
—