NPRR #306 · Revision Request
NPRR306 Revisions to Protected Information to Include Black Start Documents Considered CEII
- PRS Mar 24 '11
- TAC Apr 7 '11
- BOARD May 17 '11
- PUCT —
ReasonThe Operations Working Group (OWG) proposes changes to the Protocols that, upon approval by the ERCOT Board, would require that Black Start Task Force (BSTF) meetings be closed to the public in order to ensure that the documents and discussions pertaining to Black Start Service are kept confidential and protected under CEII guidelines. This Protocol change would require all participants of the BSTF to sign a non-disclosure agreement.
Created2011-02-17
Approved2011-05-17
Sections Affected
1.3.6
Summary
This Nodal Protocol Revision Request (NPRR) revises Section 1.3.6 to include Black Start documents that meet the definition of Critical Energy Infrastructure Information (CEII).
Timeline
-
Jan 11
PRSFiled by OWG
-
Feb 17
PRS PRS MeetingPRSRecommended for Approval“To recommend approval of NPRR306 as submitted” — Passed→ PRS IA Review
- Feb 23
-
Mar 7
Listed without action at 1 meeting
- Mar 10
-
Mar 24
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward the 2/17/11 PRS Report and Impact Analysis for NPRR306 to TAC” — Passed→ TAC Consideration
-
Apr 7
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR306 as recommended by PRS in the 3/24/11 PRS Report” — Passed→ ERCOT Board Consideration
-
Apr 7
Listed without action at 1 meeting
- May 11
-
May 17
BOARD Board of Directors MeetingBOARDApproved“To approve NPRR306 as recommended by TAC in the 4/7/11 TAC Report.” — Passed
-
—
Posted since the last meeting