NPRR304  Removal of Frequency Bias Methodology Approval Requirement

Approved sponsor ERCOT posted 2010-12-17 ercot.com
ReasonThe responsibility for determining a methodology for frequency bias falls upon ERCOT pursuant to its roles as North American Electric Reliability Corporation (NERC) Balancing Authority and Reliability Coordinator for the ERCOT Region. See NERC Reliability Standard BAL-003-0.1b, Frequency Response and Bias. ERCOT will continue to consider input from the Performance, Disturbance, Compliance Working Group (PDCWG) or directly from TAC regarding the frequency bias methodology and the bias number calculated pursuant thereto. However, the requirement to obtain TAC approval is being eliminated to ensure that the Nodal Protocols provide ERCOT with the necessary discretion to carry out this Balancing Authority/Reliability Coordinator responsibility.
Created2011-01-20
Approved2011-04-19
Sections Affected
6.5.7.6.1
Summary
This Nodal Protocol Revision Request removes the requirement for ERCOT to develop a methodology, subject to Technical Advisory Committee (TAC) approval, to determine the optimal frequency bias for given system conditions.
Action Log 4 milestones
Documents 6
NameTypePostedClassification
304NPRR-01 Removal of Frequency Bias Methodology Approval Requir doc Dec 17 '10 Revision Request
304NPRR-02 Impact Analysis 121710 doc Dec 17 '10 Staff Report
304NPRR-03 PRS Report 012011 doc Jan 24 '11 Committee Report
304NPRR-04 PRS Report 021711 doc Feb 21 '11 Committee Report
304NPRR-05 TAC Report 030311 doc Mar 4 '11 Committee Report
304NPRR-06 Board Report 041911 doc Apr 20 '11 Committee Report
Meetings That Took It Up 5
DateMeetingCommitteeStatus
Apr 19 '11 Board of Directors Meeting BOARD Concluded
Mar 3 '11 TAC Meeting TAC Concluded
Feb 17 '11 PRS Meeting PRS Concluded
Jan 26 '11 Joint CWG/MCWG Meeting CREDITWG Concluded
Jan 20 '11 PRS Meeting PRS Concluded