NPRR #301 · Revision Request
NPRR301 Correct Energy Trade Language for Adjustment Period
- PRS Feb 17 '11
- TAC Mar 3 '11
- BOARD Apr 19 '11
- PUCT —
ReasonThe EEI Amendment recognized that a trade entered in the Adjustment Period may require time for entry and confirmation by parties in the ERCOT Systems. Therefore they have included a 30 minute period prior to the next clock hour deadline after which the trade will fall to the Hourly Reliability Unit Commitment (HRUC) that immediately follows the next HRUC execution. An alternative to this language is to strike the sentence altogether as it is now appropriately managed by the EEI language. Both options are shown below.
Created2011-01-20
Approved2011-04-19
Sections Affected
4.4.2
Summary
This Nodal Protocol Revision Request (NPRR) revises the language in Section 4.4.2 for entering Energy Trades in the Adjustment Period to match that of the latest Edison Electric Institute.(EEI) Amendment.
Timeline
- Dec 3
-
Jan 20
PRS PRS MeetingPRSRecommended for Approval“To recommend approval of NPRR301 as revised by PRS.” — Passed→ PRS review the Impact Analysis
-
Jan 26
Listed without action at 1 meeting
-
Feb 17
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward the 1/20/11 PRS Report and Impact Analysis for NPRR301 to TAC” — Passed→ TAC consideration
-
Mar 3
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR301 as recommended by PRS in the 2/17/11 PRS Report.” — Passed→ Board consideration
-
Apr 19
BOARD Board of Directors MeetingBOARDApproved“To approve NPRR301 as recommended by TAC in the 3/3/11 TAC Report” — Passed
-
—