NPRR #296 · Revision Request

NPRR296  Remove Posting Requirement for the Annual Planning Model for the CRR Auction

Approved sponsor ERCOT posted 2010-11-15 ercot.com
ReasonThe model that will be used in the CRR Annual Auction has changed since this section was written and no longer relies on the Annual Planning Model.
Created2010-12-16
Sections Affected
3.10.2
Summary
This Nodal Protocol Revision Request (NPRR) removes the requirement to post a schedule for updating transmission information for the Annual Planning Model six months prior to the annual and two-year Congestion Revenue Right (CRR) Auctions.
Action Log 4 milestones
Documents 7
NameTypePostedClassification
296NPRR-01 Remove Posting Requirement for the Annual Planning Mo doc Nov 15 '10 Revision Request
296NPRR-02 CEO Revision Request Review 111510 doc Nov 15 '10 Revision Request Comments
296NPRR-03 Impact Anaysis 111510 doc Nov 15 '10 Staff Report
296NPRR-04 PRS Report 121610 doc Dec 16 '10 Committee Report
296NPRR-05 PRS Report 012011 doc Jan 24 '11 Committee Report
296NPRR-06 TAC Report 020311 doc Feb 7 '11 Committee Report
296NPRR-07 Board Report 032211 doc Mar 22 '11 Committee Report
Meetings That Took It Up 4
DateMeetingCommitteeStatus
Feb 3 '11 TAC Meeting TAC Concluded
Jan 20 '11 PRS Meeting PRS Concluded
Jan 7 '11 Joint CWG and MCWG Meeting MCWG Concluded
Dec 16 '10 PRS Meeting PRS Concluded