ERCOT·WATCH Search ercot.com  ⌕
NPRR #294 · Revision Request

NPRR294  Texas SET 4.0 Including: Acquisition and Transfer of Customers From One REP to Another; Meter Tampering Transactional Solution

Approved sponsor Jennifer Frederick on behalf of Texas SET Working Group posted 2010-11-05 ercot.com
ReasonFacilitate the large transition of ESI IDs as a result of an acquisition pursuant to Subst. R. 25.493, Acquisition and Transfer of Customers from one Retail Electric Provider to Another, addition and removal of switch holds pursuant to P.U.C. Subst. R. 25.126, Adjustments Due to Non-Compliant Meters and Meter Tampering in Areas Where Customer Choice Has Been Introduced and P.U.C. Subst. R 25.480, Bill Payment and Adjustments.
Created2010-11-18
Approved2011-04-19
Sections Affected
1515.1.115.1.1.2.215.1.1.315.1.1.415.1.1.515.1.1.615.1.1.715.1.1.815.1.315.1.3.1 (new); 15.1.3.2 (new) 15.1.3.115.1.4.115.1.4.215.1.4.315.1.4.415.1.4.515.1.4.5.115.1.4.615.1.4.715.1.4.7.115.1.4.7.215.1.4.815.1.5.115.1.5.215.1.5.315.1.5.415.1.5.515.1.5.615.1.5.715.1.7. 15.1.815.1.9.115.1.9.215.1.9.315.1.9.415.1.1015.1.10.115.1.10.215.1.10.315.1.10.415.215.2.315.315.4.115.4.1.415.4.1.51919.3.119.4.124.124.1.124.1.2.124.1.2.224.1.3 (new)24.1.3.2 (new)24.224.3.124.3.1.424.424.4.524.5.124.6.1
Summary
This Nodal Protocol Revision Request (NPRR) defines the process for Mass Transition of Electric Service Identifiers (ESI IDs) from one Competitive Retailer (CR) to another CR when transitioning due to an acquisition, the process for switch hold indicator addition and removal, and other various changes deemed to be implemented with Texas Standard Electronic Transaction (TX SET) version 4.0. Changes to accommodate priority move-outs (including addition of the priority code and one hour processing of priority move-outs by ERCOT) and same day switches (changing the First Available Switch Date (FASD) to zero) are pending a Public Utility Commission of Texas (PUCT) rulemaking and are subject to revision.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Jan 20 '11PRS To recommend approval of NPRR294 as amended by the 1/14/11 Texas SET Working Group comments.Passed
Apr 19 '11BOARD To approve NPRR294 as amended by the 3/29/11 RMS comments.Passed
Documents 17
NameTypePostedClassification
294NPRR-01 Texas SET 4 Texas SET 4.0 Including Acquisition and T doc Nov 5 '10 Revision Request
294NPRR-02 CEO Revision Request Review 110510 doc Nov 5 '10 Revision Request Comments
294NPRR-03 ERCOT Comments 111010 doc Nov 9 '10 Revision Request Comments
294NPRR-04 RMS Comments 111110 doc Nov 11 '10 Revision Request Comments
294NPRR-05 PRS Report 111810 doc Nov 23 '10 Committee Report
294NPRR-06 Texas SET Working Group Comments 011411 doc Jan 14 '11 Revision Request Comments
294NPRR-07 RMS Comments 011911 doc Jan 19 '11 Revision Request Comments
294NPRR-08 PRS Report 012011 doc Jan 24 '11 Committee Report
294NPRR-09 Impact Analysis 021611 doc Feb 16 '11 Staff Report
294NPRR-10 Cost Benefit Analysis 021711 xls Feb 17 '11 Staff Report
294NPRR-11 PRS Report 021711 doc Feb 21 '11 Committee Report
294NPRR-12 Revised Cost Benefit Analysis 022411 xls Feb 24 '11 Staff Report
294NPRR-13 TAC Report 030311 doc Mar 3 '11 Committee Report
294NPRR-14 RMS Comments 032911 doc Mar 29 '11 Revision Request Comments
294NPRR-15 CWG Comments 040411 doc Apr 4 '11 Revision Request Comments
294NPRR-16 TAC Comments 040711 doc Apr 7 '11 Revision Request Comments
294NPRR-17 Board Report 041911 doc May 31 '12 Committee Report
Meetings That Took It Up 11
DateMeetingCommitteeStatus
Apr 19 '11 Board of Directors Meeting BOARD Concluded
Mar 3 '11 TAC Meeting TAC Concluded
Feb 17 '11 PRS Meeting PRS Concluded
Feb 16 '11 RMS Meeting RMS Concluded
Jan 26 '11 Joint CWG/MCWG Meeting CREDITWG Concluded
Jan 20 '11 PRS Meeting PRS Concluded
Jan 19 '11 RMS Meeting RMS Concluded
Dec 16 '10 PRS Meeting PRS Concluded
Dec 8 '10 RMS Meeting RMS Concluded
Nov 18 '10 PRS Meeting PRS Concluded
Nov 10 '10 RMS Meeting RMS Concluded