NPRR #276 · Revision Request
NPRR276 MIS Posting Requirement for the Network Operations Model Load Schedule
- PRS Oct 21 '10
- TAC Nov 4 '10
- BOARD Nov 16 '10
- PUCT —
ReasonInformation needs to be made available on the MIS Public Area.
Created2010-09-23
Approved2010-11-16
Sections Affected
3.10.1
Summary
This Nodal Protocol Revision Request adds a Market Information System (MIS) Public Area posting requirement for the database load schedule.
Timeline
- Sep 16
-
Sep 23
PRS PRS MeetingPRSRecommended for Approval“To recommend approval of NPRR276 as submitted” — Passed→ PRS IA Review
-
Oct 21
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward the 9/23/10 PRS Report and Impact Analysis for NPRR276 to TAC” — Passed→ TAC Consideration
-
Nov 4
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR276 as recommended by PRS in the 10/21/10 PRS Report” — Passed→ ERCOT Board Consideration
-
Nov 16
BOARDEmail Vote / Unlisted MeetingBOARDApproved“To approve NPRR276 as recommended by TAC in the 11/4/10 TAC Report.” — Passed
-
—
Posted since the last meeting