NPRR #261 · Revision Request

NPRR261  Revision of Data Submission Timeline for Network Model

Approved sponsor ERCOT posted 2010-08-08 ercot.com
ReasonThis NPRR proposes language changes to allow ERCOT to standardize the model building process to one timeline and shortens the lead time for data entry for Transmission Service Providers (TSPs), Resource Entities, and Qualified Scheduling Entities (QSEs) and allows Market Participants to standardize the data entry process into one timeline that is consistent for every month. This NPRR also clarifies ERCOT’s provides clarification of ERCOT’s requirements.
Created2010-08-19
Approved2010-10-19
Sections Affected
3.10.13.10.4
Summary
This Nodal Protocol Revision Request (NPRR) removes the three-month summer model and replaces it with individual model packages for each month. This NPRR also separates item (5) of Section 3.10.4 into three paragraphs for clarification of ERCOT’s requirements.
Action Log 4 milestones
Amendments
DateBodyMotionResult
Oct 19 '10BOARD To approve NPRR261 as amended by the 10/12/10 ERCOT commentsPassed
Documents 8
NameTypePostedClassification
261NPRR-01 Revision of Data Submission Timeline for Network Mode doc Aug 9 '10 Revision Request
261NPRR-02 CEO Revision Request Review 080910 doc Aug 9 '10 Revision Request Comments
261NPRR-03 Impact Analysis 080910 doc Aug 9 '10 Staff Report
261NPRR-04 PRS Report 081910 doc Aug 23 '10 Committee Report
261NPRR-05 PRS Report 092310 doc Sep 28 '10 Committee Report
261NPRR-06 TAC Report 100710 doc Oct 8 '10 Committee Report
261NPRR-07 ERCOT Comments 101210 doc Oct 12 '10 Revision Request Comments
261NPRR-08 Board Report 101910 doc Oct 22 '10 Committee Report
Meetings That Took It Up 3
DateMeetingCommitteeStatus
Oct 7 '10 TAC Meeting TAC Concluded
Sep 23 '10 PRS Meeting PRS Concluded
Aug 19 '10 PRS Meeting PRS Concluded