NPRR #259 · Revision Request

NPRR259  Resolution of Alignment Items A175 and A176 - Settlement of Generation Resources Dispatched to Meet System Reliability Requirements

Approved sponsor ERCOT posted 2010-07-27 ercot.com
ReasonThis change conforms the Nodal Protocols to the as-built ERCOT systems implementation and administrative controls.
Created2010-08-19
Approved2010-10-19
Sections Affected
5.16.5.9.4.1
Summary
This Nodal Protocol Revision Request (NPRR) clarifies that all commitments of a specific Generation Resource in response to an ERCOT Dispatch Instruction (whether issued electronically or verbally) for the commitment of that Generation Resource will be considered to be a Reliability Unit Commitment (RUC) and will be settled in accordance with the RUC Settlement provisions described in the Nodal Protocols.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Sep 23 '10PRS To recommend approval of NPRR259 as amended by the 9/1/10 ERCOT comments and as revised by PRS.Passed
Documents 10
NameTypePostedClassification
259NPRR-01 Resolution of Alignment Items A175 and A176 - Settlem doc Jul 28 '10 Revision Request
259NPRR-02 CEO Revision Request Review 072810 doc Jul 28 '10 Staff Report
259NPRR-03 Impact Analysis 072810 doc Jul 28 '10 Staff Report
259NPRR-04 PRS Report 081910 doc Aug 23 '10 Committee Report
259NPRR-05 ERCOT Comments 090110 doc Sep 1 '10 Revision Request Comments
259NPRR-06 PSEG TX Comments 091710 doc Sep 17 '10 Revision Request Comments
259NPRR-07 PRS Report 092310 doc Sep 27 '10 Committee Report
259NPRR-08 PRS Report 100410 doc Oct 5 '10 Committee Report
259NPRR-09 TAC Report 100710 doc Oct 8 '10 Committee Report
259NPRR-10 Board Report 101910 doc Oct 20 '10 Committee Report
Meetings That Took It Up 4
DateMeetingCommitteeStatus
Oct 7 '10 TAC Meeting TAC Concluded
Oct 4 '10 Special PRS Meeting PRS Concluded
Sep 23 '10 PRS Meeting PRS Concluded
Aug 19 '10 PRS Meeting PRS Concluded