NPRR240  Proxy Energy Offer Curve

Approved sponsor Potomac Economics posted 2010-05-25 ercot.com
ReasonClarification of responsibility and accountability for energy offers.
Created2010-06-17
Approved2010-09-21
Sections Affected
6.5.7.3
Summary
This Nodal Protocol Revision Request (NPRR) states that the Entity with decision making authority over how a Resource or Split Generation Resource is offered or scheduled shall be responsible for all offers associated with each Resource, including offers represented by a proxy Energy Offer Curve. Additional non-substantive administrative revisions, such as correcting acronym usage, are shown with the author "ERCOT Market Rules."
Action Log 5 milestones
Amendments
DateBodyMotionResult
Jul 22 '10PRS To recommend approval of NPRR240 as amended by the 7/21/10 WMS comments and as revised by PRS.Passed
Documents 21
NameTypePostedClassification
240NPRR-01 Proxy Energy Offer Curve 052610 doc May 26 '10 Revision Request
240NPRR-02 CEO Revision Request Review 052610 doc May 26 '10 Revision Request Comments
240NPRR-03 Calpine Comments 061610 doc Jun 16 '10 Revision Request Comments
240NPRR-04 PRS Report 061710 doc Jun 21 '10 Committee Report
240NPRR-05 Potomac Economics Comments 070610 doc Jul 6 '10 Revision Request Comments
240NPRR-06 WMS Comments 072110 doc Jul 21 '10 Revision Request Comments
240NPRR-07 PRS Report 072210 doc Jul 26 '10 Committee Report
240NPRR-08 Impact Analysis 072910 doc Jul 29 '10 Staff Report
240NPRR-09 Revised CEO Revision Request Review 081910 doc Aug 19 '10 Revision Request Comments
240NPRR-10 Revised Impact Analysis 081910 doc Aug 19 '10 Staff Report
240NPRR-11 PRS Report 081910 doc Aug 23 '10 Committee Report
240NPRR-12 TAC Report 090210 doc Sep 8 '10 Committee Report
240NPRR-13 Board Report 092110 doc Sep 21 '10 Committee Report
240NPRR-14 Revised Impact Analysis 060711 doc Jun 7 '11 Staff Report
240NPRR-15 Cost Benefit Analysis 062211 xls Jun 22 '11 Staff Report
240NPRR-16 PRS Report - Impact Assessment 062311 doc Jun 27 '11 Committee Report
240NPRR-17 Revised Impact Analysis 071911 doc Jul 19 '11 Staff Report
240NPRR-18 PRS Report - Impact Assessment 072111 doc Jul 25 '11 Committee Report
240NPRR-19 TAC Report - Impact Assessment 080411 doc Aug 5 '11 Committee Report
240NPRR-20 TAC Report - Impact Assessment 090111 doc Sep 2 '11 Committee Report
240NPRR-21 Board Report - Impact Assessment 092011 doc Sep 21 '11 Committee Report
Meetings That Took It Up 12
DateMeetingCommitteeStatus
Sep 20 '11 Board of Directors Meeting BOARD Concluded
Sep 1 '11 TAC Meeting TAC Concluded
Aug 4 '11 TAC Meeting TAC Concluded
Jul 21 '11 PRS Meeting PRS Concluded
Jun 23 '11 PRS Meeting PRS Concluded
Sep 2 '10 TAC Meeting TAC Concluded
Aug 19 '10 PRS Meeting PRS Concluded
Jul 22 '10 PRS Meeting PRS Concluded
Jul 21 '10 WMS Meeting WMS Concluded
Jun 23 '10 NATF Meeting NATF Concluded
Jun 17 '10 PRS Meeting PRS Concluded
Jun 16 '10 WMS Meeting WMS Concluded