NPRR #240 · Revision Request
NPRR240 Proxy Energy Offer Curve
ReasonClarification of responsibility and accountability for energy offers.
Created2010-06-17
Approved2010-09-21
Sections Affected
6.5.7.3
Summary
This Nodal Protocol Revision Request (NPRR) states that the Entity with decision making authority over how a Resource or Split Generation Resource is offered or scheduled shall be responsible for all offers associated with each Resource, including offers represented by a proxy Energy Offer Curve. Additional non-substantive administrative revisions, such as correcting acronym usage, are shown with the author "ERCOT Market Rules."
Action Log 5 milestones
-
Jul 22
PRSRecommended for Approval→ PRS Impact Analysis review
-
Jun 17
PRSDeferred/Tabled→ PRS language consideration
-
Aug 19
PRSRecommended for Approval→ TAC consideration of NPRR240
-
Sep 2
TACRecommended for Approval→ ERCOT Board consideration of NPRR240
-
Sep 21
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Jul 22 '10 | PRS | To recommend approval of NPRR240 as amended by the 7/21/10 WMS comments and as revised by PRS. | Passed |
Documents 21
Meetings That Took It Up 12
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Sep 20 '11 | Board of Directors Meeting | BOARD | Concluded |
| Sep 1 '11 | TAC Meeting | TAC | Concluded |
| Aug 4 '11 | TAC Meeting | TAC | Concluded |
| Jul 21 '11 | PRS Meeting | PRS | Concluded |
| Jun 23 '11 | PRS Meeting | PRS | Concluded |
| Sep 2 '10 | TAC Meeting | TAC | Concluded |
| Aug 19 '10 | PRS Meeting | PRS | Concluded |
| Jul 22 '10 | PRS Meeting | PRS | Concluded |
| Jul 21 '10 | WMS Meeting | WMS | Concluded |
| Jun 23 '10 | NATF Meeting | NATF | Concluded |
| Jun 17 '10 | PRS Meeting | PRS | Concluded |
| Jun 16 '10 | WMS Meeting | WMS | Concluded |