NPRR #219 · Revision Request
NPRR219 Resolution of Alignment Items A33, A92, A106, and A150 - TSPs Must Submit Outages for Resource Owned Equipment and Clarification of Changes in Status of Transmission Element Postings
ReasonThis change conforms the Nodal Protocols to the as-built Nodal system.
Created2010-04-22
Approved2015-02-10
Sections Affected
2.13.1.5.13.3.2.16.3.2
Summary
This Nodal Protocol Revision Request (NPRR) will require the Resource Entity to designate a Transmission Service Provider (TSP) as the responsible Entity that will manage Outage Scheduler entries for the Resource Entity for Transmission Elements owned by the Resource other than the outage of the Generation or Load Resource itself. This NPRR will also require all changes or expected changes in the status of Transmission Facilities to be in the Outage Scheduler to ensure that all Outages in the Outage Scheduler are provided to the Market Information System (MIS).
Action Log 10 milestones
-
May 20
PRSDeferred/Tabled→ PRS for language review.
-
Apr 22
PRSDeferred/Tabled→ PRS for language review.
-
Jul 22
PRSDeferred/Tabled→ PRS for consideration.
-
Jun 17
PRSDeferred/Tabled→ PRS for consideration.
-
Aug 19
PRSDeferred/Tabled→ PRS for language consideration.
-
Sep 23
PRSDeferred/Tabled→ PRS Consideration
-
Oct 4
PRSRecommended for Approval→ TAC for consideration.
-
Oct 7
TACRecommended for Approval→ ERCOT Board for consideration.
-
Oct 19
BOARDApproved→ Parking Deck - Impact Analysis and Cost Benefit Analysis Review
-
Feb 10
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Oct 4 '10 | PRS | To recommend approval of NPRR219 as amended by the 9/22/10 TIEC comments and as revised by PRS and to forward NPRR219 and the Impact Analysis to TAC via roll call vote. | Passed |
| Oct 7 '10 | TAC | To recommend approval of NPRR219 as recommended by PRS in the 10/4/10 PRS Report as revised by TAC and to recommend a priority of Critical to the grey-boxed language. | Passed |
| Oct 19 '10 | BOARD | To approve NPRR219 as recommended by TAC in the 10/7/10 TAC Report and as amended by the 10/14/10 ERCOT comments. | Passed |
Documents 41
| Name | Type | Posted | Classification |
|---|---|---|---|
| 219NPRR-01 Resolution of Alignment Items A33, A92, A106, and A15 | doc | Mar 24 '10 | Revision Request |
| 219NPRR-02 CEO Revision Request Review 032410 | doc | Mar 24 '10 | Staff Report |
| 219NPRR-03 Impact Analysis 032410 | doc | Mar 24 '10 | Staff Report |
| 219NPRR-04 Luminant Energy Comments 033110 | doc | Mar 31 '10 | Revision Request Comments |
| 219NPRR-05 PRS Report 042210 | doc | Apr 27 '10 | Committee Report |
| 219NPRR-06 Market Participant Workshop Comments 051710 | doc | May 17 '10 | Revision Request Comments |
| 219NPRR-07 TIEC Comments 051810 | doc | May 18 '10 | Revision Request Comments |
| 219NPRR-08 PRS Report 052010 | doc | May 25 '10 | Committee Report |
| 219NPRR-09 ERCOT Comments 061610 | doc | Jun 16 '10 | Revision Request Comments |
| 219NPRR-10 PRS Report 061710 | doc | Jun 21 '10 | Committee Report |
| 219NPRR-11 CenterPoint Energy Comments 071210 | doc | Jul 12 '10 | Revision Request Comments |
| 219NPRR-12 PRS Report 072210 | doc | Jul 27 '10 | Committee Report |
| 219NPRR-13 TIEC Comments 081810 | doc | Aug 18 '10 | Revision Request Comments |
| 219NPRR-14 PRS Report 081910 | doc | Aug 23 '10 | Committee Report |
| 219NPRR-15 ERCOT Comments 091610 | doc | Sep 16 '10 | Revision Request Comments |
| 219NPRR-16 ROS Comments 092110 | doc | Sep 21 '10 | Revision Request Comments |
| 219NPRR-17 LCRA Comments 092210 | doc | Sep 22 '10 | Revision Request Comments |
| 219NPRR-18 TIEC Comments 092210 | doc | Sep 22 '10 | Revision Request Comments |
| 219NPRR-19 PRS Report 092310 | doc | Sep 27 '10 | Committee Report |
| 219NPRR-20 Oncor Comments 100110 | doc | Oct 1 '10 | Revision Request Comments |
| 219NPRR-21 CenterPoint Energy Comments 100410 | doc | Oct 4 '10 | Revision Request Comments |
| 219NPRR-22 AEP Comments 100410 | doc | Oct 4 '10 | Revision Request Comments |
| 219NPRR-23 PRS Report 100410 | doc | Oct 5 '10 | Committee Report |
| 219NPRR-24 PRS Voting Ballot 100410 | xls | Oct 5 '10 | Revision Request Ballot |
| 219NPRR-25 Revised CEO Revision Request Review 100610 | doc | Oct 7 '10 | Committee Report |
| 219NPRR-26 Revised Impact Analysis 100610 | doc | Oct 7 '10 | Staff Report |
| 219NPRR-27 TAC Report 100710 | doc | Oct 8 '10 | Committee Report |
| 219NPRR-28 ERCOT Comments 101210 | doc | Oct 12 '10 | Revision Request Comments |
| 219NPRR-29 ERCOT Comments 101410 | doc | Oct 14 '10 | Revision Request Comments |
| 219NPRR-30 Board Report 101910 | doc | Oct 21 '10 | Committee Report |
| 219NPRR-31 Revised Impact Analysis 013111 | doc | Jan 31 '11 | Staff Report |
| 219NPRR-32 Cost Benefit Analysis 013111 | xls | Jan 31 '11 | Committee Report |
| 219NPRR-33 PRS Report - Impact Assessment 021711 | doc | Feb 22 '11 | Committee Report |
| 219NPRR-34 TAC Report - Impact Assessment 030311 | doc | Mar 4 '11 | Committee Report |
| 219NPRR-35 ROS Comments 111212 | doc | Nov 12 '12 | Revision Request Comments |
| 219NPRR-36 Revised Impact Analysis 031714 | doc | Mar 17 '14 | Staff Report |
| 219NPRR-37 Luminant Comments 011415 | doc | Jan 19 '15 | Revision Request Comments |
| 219NPRR-38 PRS Report 011515 | doc | Jan 20 '15 | Committee Report |
| 219NPRR-39 American Electric Power Service Corporation Comments 012315 | doc | Jan 23 '15 | Revision Request Comments |
| 219NPRR-40 TAC Report 012915 | doc | Jan 29 '15 | Committee Report |
| 219NPRR-41 Board Report 021015 | doc | Feb 11 '15 | Committee Report |
Meetings That Took It Up 74