NPRR215  Resolution of Alignment Item A151 - Removal of Posting Requirement for RMR Services

Withdrawn sponsor ERCOT posted 2010-03-15 ercot.com
ReasonThe posting of RMR units’ actual dispatch MWh along with all other Generation Resources will be provided in the 60 day posting requirement under Section 3.2.5, Publication of Resource and Load Information. A special posting for this item is not required or currently in the scope of the nodal system implementation.
Created2010-03-25
Sections Affected
6.3.2
Summary
This Nodal Protocol Revision Request (NPRR) removes the redundant posting of Reliability Must-Run (RMR) energy deployment.
Action Log 1 milestones
Documents 8
NameTypePostedClassification
215NPRR-01 Resolution of Alignment Item A151 - Removal of Postin doc Mar 15 '10 Revision Request
215NPRR-02 CEO Revision Request Review 031510 doc Mar 15 '10 Committee Report
215NPRR-03 Impact Analysis 031510 doc Mar 15 '10 Staff Report
215NPRR-04 Reliant Energy Comments 032210 doc Mar 22 '10 Revision Request Comments
215NPRR-05 PSEG TX Comments 032310 doc Mar 23 '10 Revision Request Comments
215NPRR-06 PRS Report 032510 doc Mar 26 '10 Committee Report
215NPRR-07 PSEG TX Comments 041410 doc Apr 14 '10 Revision Request Comments
215NPRR-08 Request for Withdrawal 042110 doc Apr 21 '10 Revision Request Comments
Meetings That Took It Up 2
DateMeetingCommitteeStatus
Apr 22 '10 PRS Meeting PRS Concluded