NPRR #208 · Revision Request
NPRR208 Registration and Settlement of Distributed Generation (DG) Less Than One MW
ReasonThe reason for this revision is to incorporate changes approved in PRR756, clarified registration requirements for DG to allow all DG to be settled as negative Load and raise the threshold for DG that can be settled as negative Load. PRR756 language established the threshold for Distributed Renewable Generation (DRG) negative Load Settlement at less than fifty (50) kW. This NPRR establishes a DG registration threshold.
Created2010-02-18
Approved2010-07-20
Sections Affected
2.1Definitions 2.2Acronyms 10.2.2TSP and DSP Metered Entities 11.4.4.2Load Reduction for Excess PhotoVoltaic Distributed Renewable Generation 11.4.4.3Load Reduction for Excess Non-PhotoVoltaic Distributed Generation 16.5Registration of Generation ResourcesLoads Acting as a Resource and Emergency Interruptible Load Service Resources 18.2Methodology 18.2.2Load Profiles for Non-Interval Metered Loads 18.2.3Load Profiles for Non-Metered Loads
Summary
The Nodal Protocol Revision Request (NPRR) includes proposed language changes by the NOIE DRG Taskforce in regards to the registration requirements for Distributed Generation (DG) greater than 50 kW and less than or equal to one MW. In addition this NPRR synchronizes language approved through PRR756, Distributed Renewable Generation Modifications, with some recommended revisions consistent with the NOIE DRG Task force discussions. PRR756 was approved by ERCOT Board on 5/20/08 and was un-grey boxed upon system implementation on 11/21/09.
Action Log 9 milestones
-
Jul 1
TACRecommended for Approval→ ERCOT Board consideration
-
Jun 8
COPSRecommended for Approval→ TAC consideration
-
May 6
TACRecommended for Approval→ BOD consideration
-
Feb 18
PRSRecommended for Approval→ PRS consider the Recommendation Report and Impact Analysis
-
Mar 25
PRSRecommended for Approval→ TAC consideration
-
Jul 20
BOARDApproved
-
Apr 8
TACDeferred/Tabled→ TAC consideration
-
May 18
BOARDRemanded→ TAC consideration
-
Jun 3
TACReferred→ COPS consideration
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Jul 1 '10 | TAC | To recommend approval of NPRR208 as amended by the 06/24/10 ERCOT comments and to assign a priority of High/Medium to the grey-boxed language. | Passed |
| Jun 8 '10 | COPS | To recommend approval of NPRR208 as amended by COPS. | Passed |
| May 6 '10 | TAC | To recommend approval of NPRR208 as recommended by PRS in the 03/25/10 PRS Report as revised by TAC. | Passed |
| Feb 18 '10 | PRS | To recommend approval of NPRR208 as amended by the 1/29/10 PWG comments. | Passed |
| Mar 25 '10 | PRS | To endorse and forward the 2/18/10 PRS Report as amended by the 3/3/10 ERCOT comments and as revised by PRS and Impact Analysis for NPRR208 to TAC | Passed |
Documents 34
Meetings That Took It Up 26
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Mar 3 '11 | TAC Meeting | TAC | Concluded |
| Feb 17 '11 | PRS Meeting | PRS | Concluded |
| Jan 26 '11 | PWG Meeting via WebEx | PWG | Concluded |
| Dec 9 '10 | PWG Meeting via WebEx | PWG | Concluded |
| Nov 11 '10 | PWG Meeting via WebEx | PWG | Concluded |
| Nov 4 '10 | TAC Meeting | TAC | Concluded |
| Oct 27 '10 | PWG Meeting | PWG | Concluded |
| Oct 12 '10 | COPS Meeting | COPS | Concluded |
| Sep 22 '10 | PWG Meeting | PWG | Concluded |
| Aug 25 '10 | PWG Meeting | PWG | Concluded |
| Jul 1 '10 | TAC Meeting | TAC | Concluded |
| Jun 8 '10 | COPS Meeting | COPS | Concluded |
| Jun 3 '10 | TAC Meeting | TAC | Concluded |
| May 26 '10 | PWG Meeting | PWG | Concluded |
| May 25 '10 | PWG Meeting | PWG | Concluded |
| May 6 '10 | TAC Meeting | TAC | Concluded |
| Apr 28 '10 | PWG Meeting | PWG | Concluded |
| Apr 9 '10 | Metering Working Group Meeting | MWG | Concluded |
| Apr 8 '10 | TAC Meeting | TAC | Concluded |
| Mar 25 '10 | PRS Meeting | PRS | Concluded |
| Mar 24 '10 | PWG Meeting | PWG | Concluded |
| Mar 10 '10 | Credit Work Group Meeting | CREDITWG | Concluded |
| Feb 18 '10 | PRS Meeting | PRS | Concluded |
| Feb 10 '10 | RMS Meeting | RMS | Concluded |
| Feb 9 '10 | COPS Meeting | COPS | Concluded |
| Jan 27 '10 | PWG Meeting via WebEx | PWG | Concluded |