NPRR #205 · Revision Request
NPRR205 Transmission and/or Distribution Service Provider (TDSP) Definition Revision
- PRS Feb 18 '10
- TAC May 6 '10
- BOARD May 18 '10
- PUCT —
ReasonThe current definition of TDSP is partially limited to new Entities that were selected to own and operate Transmission Facilities as part of the PUCT Order for Docket No. 35665, Commission Staff’s Petition for the Selection of Entities Responsible for Transmission Improvements Necessary to Deliver Renewable Energy from Competitive Renewable Energy Zones. This NPRR would allow for any Entity that was selected to own and operate Transmission Facilities and has a code of conduct approved by the PUCT to be a TDSP and not limit to only those Entities approved in Docket No. 35665.
Created2010-02-18
Approved2010-05-18
Sections Affected
2.1Definitions
Summary
This Nodal Protocol Revision Request (NPRR) revises the definition of Transmission and/or Service Provider (TDSP) to include Entities that have been selected to own and operate Transmission Facilities and have a code of conduct approved by the Public Utility Commission of Texas (PUCT).
Timeline
-
Jan 15
PRSFiled by Mike Grable on behalf of ERCOT
-
Feb 18
PRS PRS MeetingPRSRecommended for Approval Amended by the Jan 22 '10 CenterPoint Energy comments“To recommend approval of NPRR205 as amended by the 1/22/10 CenterPoint Energy comments.” — Passed→ PRS consider the Recommendation Report and IA.
- Mar 10
-
Mar 25
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward the 2/18/10 PRS Report and Impact Analysis for NPRR205 to TAC” — Passed→ TAC consideration
- Apr 8
-
May 6
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR205 as recommended by PRS in the 3/25/10 PRS Report.” — Passed→ BOD consideration
-
May 18
BOARDEmail Vote / Unlisted MeetingBOARDApproved“To approve NPRR205 as recommended by TAC in the 5/6/10 TAC Report.” — Passed