NPRR #199 · Revision Request
NPRR199 Shift Factors by Resource Node
ReasonThe requirement for ERCOT to provide Shift Factors by Resource Node is not currently in the Protocols.
Created2009-12-17
Approved2010-02-16
Sections Affected
4.2.3
Summary
This Nodal Protocol Revision Requests (NPRR) adds the reporting requirement for ERCOT to provide Shift Factors by Resource Node.
Action Log 4 milestones
-
Feb 4
TACRecommended for Approval→ ERCOT Board for consideration.
-
Jan 26
PRSRecommended for Approval→ TAC for consideration.
-
Feb 16
BOARDApproved
-
Dec 17
PRSRecommended for Approval→ PRS for Impact Analysis review.
Documents 7
| Name | Type | Posted | Classification |
|---|---|---|---|
| 199NPRR-01 Shift Factors by Resource Node Report 112009 | doc | Nov 20 '09 | Revision Request |
| 199NPRR-02 CEO Revision Request Review 112009 | doc | Nov 20 '09 | Revision Request Comments |
| 199NPRR-03 PRS Recommendation Report 121709 | doc | Dec 17 '09 | Committee Report |
| 199NPRR-04 Impact Analysis 010410 | doc | Jan 4 '10 | Staff Report |
| 199NPRR-05 PRS Report 012110 | doc | Jan 22 '10 | Committee Report |
| 199NPRR-06 TAC Report 020410 | doc | Feb 5 '10 | Committee Report |
| 199NPRR-07 Board Report 021610 | doc | Feb 16 '10 | Committee Report |
Meetings That Took It Up 4
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Feb 4 '10 | TAC Meeting | TAC | Concluded |
| Jan 21 '10 | PRS Meeting | PRS | Concluded |
| Jan 11 '10 | Joint Credit Work Group and Market Credit Working Group Meeting | CREDITWG | Concluded |
| Dec 17 '09 | PRS Meeting | PRS | Concluded |