NPRR #188 · Revision Request

NPRR188  MVA for SCED Input

Approved sponsor Ebby John on behalf of the Network Data Support Working Group (NDSWG) posted 2009-07-10 ercot.com
ReasonMVA values from a TSP or any Market Participant are not used within State Estimator solutions except in the case of a Dynamic Rating. The ERCOT Energy Management System (EMS) is not designed to accept MVA values for equipment except as a Dynamic Rating. The ERCOT State Estimator, and subsequently contingency analysis, utilizes MW and Mega Volt-Amperes reactive (MVAr) Inter-Control Center Communications Protocol (ICCP) data to determine an MVA value which then may be passed to SCED if needed. The State Estimator/contingency analysis-determined MVA value is used to compare with the Market Participant provided ratings, including Dynamic Ratings, and is captured as a Real-Time sequence and SCED requirement pursuant to paragraph (1) (b) of Section 6.5.7.1.13. This NPRR also replaces CIM with Network Operations Model as Common Information Model (CIM) is a format. All MVA ratings are provided and are utilized by ERCOT in maintaining the reliability of the ERCOT Transmission Grid.
Created2009-07-23
Approved2009-09-15
Sections Affected
6.5.7.1.13
Summary
This Nodal Protocol Revision Request (NPRR) removes the Transmission Service Provider (TSP) requirement to provide MVA to be used in Real-Time sequence and Security-Constrained Economic Dispatch (SCED). This NPRR also corrects the use of Common Information Model (CIM) and corrects the Dynamic Rating requirement.
Action Log 4 milestones
Documents 9
NameTypePostedClassification
188NPRR-01 MVA for SCED Input 071009 doc Jul 10 '09 Revision Request
188NPRR-02 CEO Revision Request Review 071009 doc Jul 10 '09 Revision Request Comments
188NPRR-03 ERCOT Comments 072209 doc Jul 22 '09 Revision Request Comments
188NPRR-04 Austin Energy Comments 072209 doc Jul 22 '09 Revision Request Comments
188NPRR-05 PRS Recommendation Report 072309 doc Jul 24 '09 Committee Report
188NPRR-06 Impact Analysis 082009 doc Aug 20 '09 Staff Report
188NPRR-07 PRS Recommendation Report 082509 doc Aug 27 '09 Committee Report
188NPRR-08 TAC Recommendation Report 090309 doc Sep 3 '09 Committee Report
188NPRR-09 Board Action Report 091509 doc Sep 16 '09 Committee Report
Meetings That Took It Up 4
DateMeetingCommitteeStatus
Sep 3 '09 TAC Meeting TAC Concluded
Aug 25 '09 PRS Meeting PRS Concluded
Aug 7 '09 Credit Work Group Meeting CREDITWG Concluded
Jul 23 '09 PRS Meeting PRS Concluded