NPRR #151 · Revision Request

NPRR151  Clarify Definition of a Generator Output Breaker in the Outage Scheduler

Withdrawn sponsor Anthony Alford w/ CenterPoint Energy posted 2008-09-08 ercot.com
ReasonDepending upon the configuration of the substation could result in reliability issues when the breakers that control generating unit output are left open indefinitely, and not reported in Outage Scheduler.
Created2008-09-24
Sections Affected
3.10.7.5.1Continuous Telemetry of the Status of Breakers and Switches
Summary
This Nodal Protocol Revision Request (NPRR) clarifies the definition of which "generator output breakers" are exempt in the Outage Scheduler.
Action Log 2 milestones
Documents 9
NameTypePostedClassification
151NPRR-01 Clarify Definition of a Generator Output Breaker in t doc Sep 8 '08 Revision Request
151NPRR-02 TPTF Comments 090908 doc Sep 10 '08 Revision Request Comments
151NPRR-03 TPTF Voting Ballot- Go Live 090908 xls Feb 6 '09 Revision Request Ballot
151NPRR-04 Luminant Generation Company Comments 092308 doc Sep 23 '08 Revision Request Comments
151NPRR-05 CPS Energy Comments 092308 doc Sep 23 '08 Revision Request Comments
151NPRR-06 PRS Action Report 092408 doc Sep 29 '08 Committee Report
151NPRR-07 TPTF Comments 022309 doc Feb 24 '09 Revision Request Comments
151NPRR-08 PRS Action Report 031909 doc Mar 20 '09 Committee Report
151NPRR-09 Request for Withdrawal 032609 doc Mar 26 '09 Revision Request Comments
Meetings That Took It Up 5
DateMeetingCommitteeStatus
Apr 23 '09 PRS Meeting PRS Concluded
Mar 19 '09 PRS Meeting PRS Concluded
Feb 23 '09 TPTF Meeting TPTF Concluded
Oct 13 '08 TPTF Meeting TPTF Concluded
Sep 24 '08 PRS Meeting PRS Concluded