NPRR #144 · Revision Request
NPRR144 Five RUC Deployments Needed Before Requiring Verifiable Costs
- PRS Aug 21 '08
- TAC Oct 2 '08
- BOARD Oct 21 '08
- PUCT —
ReasonThis NPRR should avoid unnecessary collection and approving of verifiable cost submissions for Resources that are unlikely to receive RUC instructions.
Created2008-08-21
Approved2008-10-21
Sections Affected
Section 5.6.1Verifiable Costs
Summary
This Nodal Protocol Revision Request (NPRR) will increase the time Qualified Scheduling Entities (QSEs) and Resources have to prepare verifiable cost submissions for units that are unlikely to be struck in the Reliability Unit Commitment (RUC) process.
Timeline
-
Jul 25
PRSFiled by Heddie Lookadoo on behalf of the VCWG
-
Aug 11
Listed without action at 1 meeting
-
Aug 21
PRS PRS MeetingPRSRecommended for Approval Amended by the TPTF comments“To recommend approval of NPRR144 as amended by TPTF comments.” — Passed→ PRS for review of the Impact Analysis and Recommendation Report.
-
Aug 22
Listed without action at 1 meeting
- Sep 12
-
Sep 24
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward the PRS Recommendation Report and Impact Analysis to TAC.” — Passed→ TAC consideration
-
Oct 2
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR144 as recommended by PRS.” — Passed→ Board consideration
-
Oct 21
BOARDEmail Vote / Unlisted MeetingBOARDApproved“The ERCOT Board approved NPRR144 as recommended by TAC.” — Passed