NPRR #141 · Revision Request
NPRR141 TSP Energy Storage for Reliability (formerly "TSP and/or DSP Energy Storage for Reliability")
ReasonThis NPRR seeks to clarify that energy, associated with the charging and discharging of TSP owned battery storage technology, will not be measured for the purposes of settlement.
Created2008-08-21
Approved2009-06-16
Sections Affected
10.3.3.1
Summary
This Nodal Protocol Revision Request (NPRR) inserts new paragraph (f)(iii) in Section 10.3.3.1 that clarifies that metering of energy flows from Transmission Service Provider (TSP) owned battery storage technology is not required for Settlement. This new paragraph will be limited to the Presidio substation Facilities.
Action Log 5 milestones
-
Apr 23
PRSRecommended for Approval→ PRS Impact Analysis review
-
Aug 21
PRSDeferred/Tabled→ PRS language consideration
-
May 21
PRSRecommended for Approval→ TAC consideration of NPRR141
-
Jun 16
BOARDApproved
-
Jun 4
TACRecommended for Approval→ ERCOT Board consideration of NPRR141
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Apr 23 '09 | PRS | To recommend approval of NPRR141 as amended by TPTF comments. | Passed |
| Jun 4 '09 | TAC | To recommend approval of NPRR141 as amended by ERCOT comments. | Passed |
Documents 13
Meetings That Took It Up 8
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jun 16 '09 | ERCOT Board of Directors Meeting | BOARD | Concluded |
| Jun 4 '09 | TAC Meeting | TAC | Concluded |
| May 21 '09 | PRS Meeting | PRS | Concluded |
| Apr 23 '09 | PRS Meeting | PRS | Concluded |
| Feb 23 '09 | TPTF Meeting | TPTF | Concluded |
| Aug 25 '08 | TPTF Meeting | TPTF | Concluded |
| Aug 21 '08 | PRS Meeting | PRS | Concluded |
| Aug 11 '08 | TPTF Meeting | TPTF | Concluded |