NPRR #139 · Revision Request
NPRR139 ACL, EAL, FCE Calculation Updates
ReasonEliminate duplication with FCE component for establishing a forward value for CRR activity. Provide more flexibility for entities to prepay invoices Auction clearing price is as appropriate as the Hub price to replace a missing DAM Settlement Point Price and is more readily available Clarify the intent of the ACL.
Created2008-08-21
Approved2008-11-17
Sections Affected
16.11.4.3; 16.11.4.5; 16.11.4.6
Summary
Congestion Revenue Right’s (CRR’s) future exposure is represented by Future Credit Exposure (FCE) calculations. Including the CRR Invoices in Daily DA Liability Extrapolated (DALE) and Average Daily Transaction Extrapolated (ADTE) calculations result in calculating the future exposure more than once for CRR activity. Hence the CRR activity needs to be excluded from DALE and ADTE calculations. Eliminate the "two day" requirement for prepays. Invoices will be removed from the exposure calculation the day after they are paid. If the Day Ahead Market (DAM) is executed but specific DAM Settlement Point Prices are not available, ERCOT may use the appropriate auction clearing prices instead. 90% was mentioned twice, once in Available Credit Limit (ACL) definition and once in CRR auction credit limit. The intention is to apply 90% to ACL only once. Hence the 90% is removed from the ACL definition.
Action Log 5 milestones
-
Sep 24
PRSRecommended for Approval→ PRS consideration of Impact Analysis
-
Oct 23
PRSRecommended for Approval→ TAC for consideration.
-
Nov 6
TACRecommended for Approval→ Board consideration
-
Nov 17
BOARDApproved
-
Aug 21
PRSReferred→ PRS for consideration.
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Sep 24 '08 | PRS | To recommend approval of NPRR139 as amended by TPTF comments. | Passed |
Documents 10
| Name | Type | Posted | Classification |
|---|---|---|---|
| 139NPRR -01 ACL, EAL, FCE Calculation Updates 071108 | doc | Sep 2 '08 | Revision Request |
| 139NPRR-02 PRS Action Report 082108 | doc | Aug 26 '08 | Committee Report |
| 139NPRR-03 TPTF Comments 090208 | doc | Sep 2 '08 | Revision Request Comments |
| 139NPRR-04 TPTF Ballot 090208 | xls | Sep 5 '08 | Revision Request Ballot |
| 139NPRR-05 PRS Recommendation Report 092408 | doc | Sep 29 '08 | Committee Report |
| 139NPRR-06 Impact Analysis 101608 | doc | Oct 16 '08 | Staff Report |
| 139NPRR-07 Revised Impact Analysis 102208 | doc | Oct 22 '08 | Staff Report |
| 139NPRR-08 PRS Recommendation Report 102308 | doc | Oct 27 '08 | Committee Report |
| 139NPRR-09 TAC Recommendation Report 110608 | doc | Nov 6 '08 | Committee Report |
| 139NPRR-10 Board Action Report 111708 | doc | Nov 18 '08 | Committee Report |
Meetings That Took It Up 5
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Nov 6 '08 | TAC Meeting | TAC | Concluded |
| Oct 23 '08 | PRS Meeting | PRS | Concluded |
| Sep 24 '08 | PRS Meeting | PRS | Concluded |
| Aug 25 '08 | TPTF Meeting | TPTF | Concluded |
| Aug 21 '08 | PRS Meeting | PRS | Concluded |