NPRR #1340 · Revision Request
NPRR1340 Dispatchable Reliability Reserve Service Ancillary Service with Energy Storage Resource Participation
- PRS now · Consideration
- TAC
- BOARD
- PUCT
ReasonRegulatory requirements
Created2026-07-15
Sections Affected
3.17.5 (new)3.184.5.15.7.4.1.16.5.7.3and 6.5.7.5
Summary
This Nodal Protocol Revision Request (NPRR) adds Energy Storage Resource (ESR) participation to the Dispatchable Reliability Reserve Service (DRRS) Ancillary Service. In addition to eligible Off-Line Generation Resources and On-Line Generation Resources, this provides the framework for ESRs to provide DRRS. ESR participation in DRRS would only be permitted using the discharge capability, not the charging capability (i.e., positive High Sustained Limit (HSL)).
Timeline
- May 29
- Jul 9
-
Jul 15
PRS PRS MeetingPRSDeferred/Tabled Referred → ROS Referred → WMS“To table NPRR1340 and refer the issue to ROS and WMS” — Passed→ PRS for consideration
- Jul 27
- Aug 5
- Aug 6
- Aug 12
- Aug 19
-
Aug 25
Listed without action at 1 meeting