NPRR #1329 · Revision Request
NPRR1329 Resource Entity Requirements for Self-Limiting Facilities
ReasonStrategic Plan Objective 3
Created2026-05-06
Sections Affected
3.8.7
Summary
This Nodal Protocol Revision Request (NPRR) establishes a framework whereby two Resource Entities and their associated Qualified Scheduling Entities (QSEs) may jointly share the responsibility for managing the injection and withdrawal limits at a Point of Interconnection (POI) and formalizes the responsible QSE functions through an attestation process that is deemed acceptable to ERCOT.
Action Log 2 milestones
-
May 6
PRSRecommended for Approval→ Impact Analysis Consideration
-
Jun 10
PRSDeferred/Tabled→ Impact Analysis Consideration
Ballots
| Date | Body | Result | Yes | No | Abstain | |
|---|---|---|---|---|---|---|
| Jun 10 '26 | PRS | Motion Carries | 7 | 0 | 0 | xls |
| May 6 '26 | PRS | Motion Carries | 7 | 0 | 0 | xls |
Documents 7
| Name | Type | Posted | Classification |
|---|---|---|---|
| 1329NPRR-01 Resource Entity Requirements for Self-Limiting Facilities 041326 | docx | Apr 13 '26 | Revision Request |
| 1329NPRR-02 PRS Ballot 050626 | xls | May 11 '26 | Revision Request Ballot |
| 1329NPRR-03 PRS Report 050626 | docx | May 11 '26 | Committee Report |
| 1329NPRR-04 ERCOT Comments 060226 | docx | Jun 2 '26 | Revision Request Comments |
| 1329NPRR-05 PRS Ballot 061026 | xls | Jun 15 '26 | Revision Request Ballot |
| 1329NPRR-06 PRS Report 061026 | docx | Jun 15 '26 | Committee Report |
| 1329NPRR-07 ERCOT Comments 071326 | docx | Jul 13 '26 | Revision Request Comments |
Meetings That Took It Up 3
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jul 15 '26 | PRS Meeting | PRS | Scheduled |
| Jun 10 '26 | PRS Meeting | PRS | Concluded |
| May 6 '26 | PRS Meeting | PRS | Concluded |