Withdrawn sponsor Joint Sponsors posted 2026-02-03 ercot.com
ReasonStrategic Plan Objective 1
Created2026-03-11
Sections Affected
3.11.4.12 (new)
Summary
This NPRR enables ERCOT to perform a “Batch Alpha” interconnection study for Large Loads by using an existing process (the Regional Planning Group (RPG) process) with clearly defined timelines and inclusion criteria. Importantly, this will allow ERCOT to achieve aggressive timelines for implementation without requiring the need for a good cause exception to the Protocols.
Action Log 1 milestones
Ballots
DateBodyResultYesNoAbstain
Mar 11 '26 PRS Motion Carries 7 0 0 xls
Documents 6
NameTypePostedClassification
1321NPRR-01 Batch Alpha 020326 docx Feb 3 '26 Revision Request
1321NPRR-02 Schaper Energy Consulting Comments 020826 docx Feb 8 '26 Revision Request Comments
1321NPRR-03 ERCOT Comments 021126 docx Feb 11 '26 Revision Request Comments
1321NPRR-04 PRS Ballot 031126 xls Mar 11 '26 Revision Request Ballot
1321NPRR-05 PRS Report 031126 docx Mar 11 '26 Committee Report
1321NPRR-06 Request for Withdrawal 060226 docx Jun 2 '26 Revision Request
Meetings That Took It Up 5
DateMeetingCommitteeStatus
Jun 10 '26 PRS Meeting PRS Concluded
May 6 '26 PRS Meeting PRS Concluded
Apr 15 '26 PRS Meeting PRS Concluded
Mar 11 '26 PRS Meeting PRS Concluded
Feb 11 '26 PRS Meeting PRS Concluded