NPRR #1300 · Revision Request
NPRR1300 Protected Information and ECEII to OPUC
- PRS Nov 12 '25
- TAC Nov 19 '25
- BOARD Dec 8 '25
- PUCT Jan 15 '26
ReasonRegulatory requirements
Created2025-10-08
Approved2026-01-15
Sections Affected
1.3 and 1.3.6
Summary
This Nodal Protocol Revision Request (NPRR) implements Senate Bill 1877 (SB 1877) by including the Office of Public Utility Counsel (OPUC) as an entity that is permitted to receive Protected Information or ERCOT Critical Energy Infrastructure Information (ECEII) without violating Protocols Section 1.3, Confidentiality.
Timeline
- Sep 11
-
Oct 8
PRS PRS MeetingPRSRecommended for Approval“to recommend approval of NPRR1300 as submitted” — Passed→ Impact Analysis Consideration
-
Nov 12
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“to endorse and forward to TAC the 10/8/25 PRS Report and 9/11/25 Impact Analysis for NPRR1300” — Passed→ Revision Request Consideration
-
Nov 19
TAC TAC MeetingTACRecommended for Approval“to recommend approval of NPRR1300 as recommended by PRS in the 11/12/25 PRS Report” — Passed→ Revision Request Consideration
-
Dec 8
BOARD Board of Directors MeetingBOARDRecommended for Approval“recommended approval of NPRR1300 as recommended by TAC in the 11/19/25 TAC Report.” — Passed→ Revision Request Consideration
-
Jan 15
PUCTPUCTApproved“to approve NPRR1300 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
-
—
Posted since the last meeting