NPRR #1296 · Revision Request
NPRR1296 Residential Demand Response Program
- PRS now · Consideration
- TAC
- BOARD
- PUCT
ReasonStrategic Plan Objective 1
Created2025-09-17
Sections Affected
2.12.23.6.13.7.1.23.14.3.13.14.3.43.14.43.26 (new)3.26.1 (new)3.26.2 (new)3.26.3 (new)3.26.4 (new)3.26.5 (new)6.9 (new)6.9.1 (new)6.9.2 (new)6.9.3 (new)8.1.4 (new)8.1.4.1 (new)8.1.4.2 (new)8.1.4.3 (new)8.1.4.4 (new)9.5.39.5.13 (new)and 22O
Summary
This Nodal Protocol Revision Request (NPRR) implements a Residential Demand Response (RDR) Program for Retail Electric Providers (REPs) and Non-Opt-In Entities (NOIEs).
Timeline
- Aug 26
-
Sep 17
PRS PRS MeetingPRSDeferred/Tabled Referred → RMS Referred → WMS“To table NPRR1296 and refer the issue to RMS and WMS” — Passed→ PRS for consideration
- Oct 3
- Oct 8
- Nov 4
-
Nov 5
Listed without action at 7 meetings (Nov 5 '25 – Jan 14 '26)
- Feb 4
-
Feb 11
Listed without action at 2 meetings (Feb 11 '26 – Feb 17 '26)
- Mar 4
-
Mar 11
Listed without action at 7 meetings (Mar 11 '26 – May 12 '26)
- Jun 3
-
Jun 10
Listed without action at 4 meetings (Jun 10 '26 – Jul 15 '26)
- Aug 5
-
Aug 11
Listed without action at 2 meetings (Aug 11 '26 – Aug 12 '26)