NPRR #1293 · Revision Request
NPRR1293 Clarifications to the Modeling Timelines
- PRS Sep 17 '25
- TAC Oct 22 '25
- BOARD Dec 8 '25
- PUCT Jan 15 '26
ReasonGeneral system and/or process improvement(s)
Created2025-08-13
Approved2026-01-15
Sections Affected
3.10.1
Summary
This Nodal Protocol Revision Request (NPRR) clarifies the 'Update Network Operations Model Production Environment' milestone dates.
Timeline
- Jul 29
-
Aug 13
PRS PRS MeetingPRSRecommended for Approval“to recommend approval of NPRR1293 as submitted” — Passed→ Impact Analysis Consideration
-
Sep 17
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“to endorse and forward to TAC the 8/13/25 PRS Report and 7/29/25 Impact Analysis for NPRR1293” — Passed→ Revision Request Consideration
-
Oct 22
TAC TAC MeetingTACRecommended for Approval“to recommend approval of NPRR1293 as recommended by PRS in the 9/17/25 PRS Report” — Passed→ Revision Request Consideration
-
Dec 8
BOARD Board of Directors MeetingBOARDRecommended for Approval“to recommend approval of NPRR1293 as recommended by TAC in the 10/22/25 TAC Report” — Passed→ Revision Request Consideration
-
Jan 15
PUCTPUCTApproved“to approve NPRR1293 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
-
—
Posted since the last meeting