NPRR #1283 · Revision Request

NPRR1283  Modification of SSR Mitigation Timeline

Approved sponsor ERCOT posted 2025-04-29 ercot.com
ReasonGeneral system and/or process improvement(s)
Created2025-05-14
Approved2025-11-06
Sections Affected
3.22.1.23.22.1.33.22.1.4and 16.5
Summary
This Nodal Protocol Revision Request (NPRR) changes the current requirement that any required SSR studies be complete and mitigation be in place prior to Initial Synchronization of a new Generation Resource, Energy Storage Resource (ESR), or Settlement Only Generator (SOG). Based on recognition that SSFR can be a risk upon energization, this NPRR requires that these steps now be completed prior to Initial Energization to ensure that SSFR risk has been evaluated and mitigated.
Action Log 6 milestones
Amendments
DateBodyMotionResult
Aug 27 '25TAC To recommend approval of NPRR1283 as recommended by PRS in the 8/13/25 PRS Report as revised by TACPassed
Ballots
DateBodyResultYesNoAbstain
Aug 27 '25 TAC Motion Passes 29 0 0 xls
Aug 13 '25 PRS Motion Carries 7 0 0 xls
Jul 16 '25 PRS Motion Carries 7 0 0 xls
Jul 10 '25 ROS Motion Carries 7.5 0 0 xls
Jun 5 '25 ROS Motion Carries 7.5 0 0 xls
May 14 '25 PRS Motion Carries 7 0 0 xls
Documents 17
NameTypePostedClassification
1283NPRR-01 Modification of SSR Mitigation Timeline 042925 docx Apr 29 '25 Revision Request
1283NPRR-02 Impact Analysis 042925 docx Apr 29 '25 Staff Report
1283NPRR-03 PRS Ballot 051425 xls May 17 '25 Revision Request Ballot
1283NPRR-04 PRS Report 051425 docx May 17 '25 Committee Report
1283NPRR-05 ROS Ballot 060625 xls Jun 6 '25 Revision Request Ballot
1283NPRR-06 ROS Comments 060625 docx Jun 6 '25 Revision Request Comments
1283NPRR-07 Joint Commenters Comments 070925 docx Jul 9 '25 Revision Request Comments
1283NPRR-08 ROS Ballot 071025 xls Jul 14 '25 Revision Request Ballot
1283NPRR-09 ROS Comments 071425 docx Jul 14 '25 Revision Request Comments
1283NPRR-10 PRS Ballot 071625 xls Jul 21 '25 Revision Request Ballot
1283NPRR-11 PRS Report 071625 docx Jul 21 '25 Committee Report
1283NPRR-12 PRS Ballot 081325 xls Aug 18 '25 Revision Request Ballot
1283NPRR-13 PRS Report 081325 docx Aug 18 '25 Committee Report
1283NPRR-14 TAC Ballot 082725 xls Sep 1 '25 Revision Request Ballot
1283NPRR-15 TAC Report 082725 docx Sep 1 '25 Committee Report
1283NPRR-16 Board Report 092225 docx Sep 24 '25 Committee Report
1283NPRR-17 PUCT Report 110625 docx Nov 10 '25 Committee Report
Meetings That Took It Up 8
DateMeetingCommitteeStatus
Sep 22 '25 Board of Directors Meeting BOARD Concluded
Aug 27 '25 TAC Meeting TAC Concluded
Aug 13 '25 PRS Meeting PRS Concluded
Jul 16 '25 PRS Meeting PRS Concluded
Jul 10 '25 ROS Meeting - Webex Only ROS Concluded
Jun 11 '25 PRS Meeting PRS Concluded
Jun 5 '25 ROS Meeting - Webex Only ROS Concluded
May 14 '25 PRS Meeting PRS Concluded