NPRR #1265 · Revision Request
NPRR1265 Unregistered Distributed Generator
- PRS Aug 13 '25
- TAC Aug 27 '25
- BOARD Sep 22 '25
- PUCT Nov 6 '25
ReasonRegulatory requirements
Created2025-01-15
Approved2025-11-06
Sections Affected
2.12.23.2.5.13.2.5.2 (delete)3.2.5.310.2.211.4.4.211.4.4.316.518.218.2.2.1and 18.2.2.2
Summary
This Nodal Protocol Provision (NPRR) implements procedures for Distributed Generation (DG) reporting provided in House Bill 3390 (HB 3390). Specifically, this NPRR clarifies the definition of “Distributed Generation (DG)” and defines a new term, “Unregistered Distributed Generators (UDG).” Additionally, this NPRR establishes procedures for UDG reporting to ERCOT and UDG reporting requirements from ERCOT. Lastly, this NPRR reconciles references to DG to UDG where the term UDG is now appropriate.
Timeline
- Dec 26
-
Jan 15
PRS PRS MeetingPRSDeferred/Tabled Referred → ROS“To table NPRR1265 and refer the issue to ROS” — Passed→ PRS for consideration
-
Feb 6
ROS ROS Meeting - Webex Only“To request PRS continue to table NPRR1265 for further review by NDSWG”
-
Feb 12
Listed without action at 6 meetings (Feb 12 '25 – May 1 '25)
- May 14
-
May 20
Listed without action at 1 meeting
- Jun 5
- Jun 11
-
Jun 17
Listed without action at 1 meeting
-
Jul 16
PRS PRS MeetingPRSRecommended for Approval Amended by the Jul 14 '25 Joint Commenters comments“To recommend approval of NPRR1265 as amended by the 7/14/25 Joint Commenters comments as revised by PRS” — Passed→ PRS for Impact Analysis consideration
-
Aug 13
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC priority 2026 · rank 400“To endorse and forward to TAC the 7/16/25 PRS Report and 12/26/24 Impact Analysis for NPRR1265 with a recommended priority of 2026 and rank of 400” — Passed→ TAC for consideration
-
Aug 27
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR1265 as recommended by PRS in the 8/13/25 PRS Report” — Passed→ Board for consideration
-
Sep 22
BOARD Board of Directors MeetingBOARDRecommended for Approval“To recommend approval of NPRR1265 as recommended by TAC in the 8/27/25 TAC Report” — Passed→ PUCT for consideration
-
Nov 6
PUCTPUCTApproved“To approve NPRR1265 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
- Jun 26