NPRR #1263 · Revision Request

NPRR1263  Clarify Testing Requirements for CCVTs

Approved sponsor WETT posted 2024-12-12 ercot.com
ReasonGeneral system and/or process improvement
Created2025-01-15
Approved2026-01-15
Sections Affected
10.6.1.2
Summary
This Nodal Protocol Revision Request (NPRR) removes the accuracy testing requirements for Coupling Capacitor Voltage Transformers (CCVTs).
Action Log 6 milestones
Amendments
DateBodyMotionResult
Sep 17 '25PRS to recommend approval of NPRR1263 as amended by the 9/9/25 Meter Working Group (MWG) commentsPassed
Ballots
DateBodyResultYesNoAbstain
Oct 22 '25 TAC Motion Passes 27 0 0 xls
Oct 8 '25 PRS Motion Carries 7 0 0 xls
Sep 17 '25 PRS Motion Carries 7 0 0 xls
Sep 10 '25 WMS 28 0 0 xls
Jan 15 '25 PRS Motion Carries 7 0 0 xls
Documents 17
NameTypePostedClassification
1263NPRR-01 Remove Accuracy Testing Requirements for CCVTs 121224 docx Dec 12 '24 Revision Request
1263NPRR-02 PRS Ballot 011525 xls Jan 21 '25 Revision Request Ballot
1263NPRR-03 PRS Report 011525 docx Jan 21 '25 Committee Report
1263NPRR-04 WMS Ballot 020525 xls Feb 6 '25 Revision Request Ballot
1263NPRR-05 WMS Comments 020625 docx Feb 6 '25 Revision Request Comments
1263NPRR-06 MWG Comments 090925 docx Sep 9 '25 Revision Request Comments
1263NPRR-07 WMS Ballot 091025 xls Sep 10 '25 Revision Request Ballot
1263NPRR-08 WMS Comments 091025 docx Sep 10 '25 Revision Request Comments
1263NPRR-09 PRS Ballot 091725 xls Sep 22 '25 Revision Request Ballot
1263NPRR-10 PRS Report 091725 docx Sep 22 '25 Committee Report
1263NPRR-11 Impact Analysis 092525 docx Sep 25 '25 Staff Report
1263NPRR-12 PRS Ballot 100825 xls Oct 13 '25 Revision Request Ballot
1263NPRR-13 PRS Report 100825 docx Oct 13 '25 Committee Report
1263NPRR-14 TAC Ballot 102225 xls Oct 26 '25 Revision Request Ballot
1263NPRR-15 TAC Report 102225 docx Oct 26 '25 Committee Report
1263NPRR-16 Board Report 120825 docx Dec 10 '25 Committee Report
1263NPRR-17 PUCT Report 011526 docx Jan 21 '26 Committee Report
Meetings That Took It Up 24
DateMeetingCommitteeStatus
Dec 8 '25 Board of Directors Meeting BOARD Concluded
Oct 22 '25 TAC Meeting TAC Concluded
Oct 8 '25 PRS Meeting PRS Concluded
Sep 17 '25 PRS Meeting PRS Concluded
Sep 10 '25 WMS Meeting WMS Concluded
Aug 27 '25 MWG Meeting - Webex Only MWG Concluded
Aug 13 '25 PRS Meeting PRS Concluded
Aug 6 '25 WMS Meeting - Webex Only WMS Concluded
Jul 23 '25 MWG Meeting - Webex Only MWG Concluded
Jul 16 '25 PRS Meeting PRS Concluded
Jul 9 '25 WMS Meeting WMS Concluded
Jun 11 '25 MWG Meeting - Webex Only MWG Concluded
Jun 11 '25 PRS Meeting PRS Concluded
Jun 4 '25 WMS Meeting - Webex Only WMS Concluded
May 14 '25 PRS Meeting PRS Concluded
May 7 '25 WMS Meeting WMS Concluded
Apr 9 '25 MWG Meeting - Webex Only MWG Concluded
Apr 9 '25 PRS Meeting PRS Concluded
Apr 2 '25 WMS Meeting WMS Concluded
Mar 12 '25 PRS Meeting PRS Concluded
Mar 5 '25 WMS Meeting - Webex Only WMS Concluded
Feb 12 '25 PRS Meeting PRS Concluded
Feb 5 '25 WMS Meeting WMS Concluded
Jan 15 '25 PRS Meeting PRS Concluded