NPRR1251  Updated FFSS Fuel Replacement Costs Recovery Process

Approved sponsor ERCOT posted 2024-08-28 ercot.com
ReasonGeneral system and/or process improvement(s)
Created2024-09-12
Approved2025-03-13
Sections Affected
3.14.5 and 6.6.14.1
Summary
This Nodal Protocol Revision Request (NPRR) implements several improvements to Firm Fuel Supply Service (FFSS) fuel cost recovery process. Specific changes include: Clarifying that Qualified Scheduling Entities (QSEs) representing FFSS Resources (FFSSRs) are able to restock reserved fuel using existing fuel inventories in storage to accelerate the restocking of fuel or based on new purchases. For fuel restocking using existing fuel inventories, the Firm Fuel Supply Service Fuel Replacement Cost may be based on: New fuel purchases made within 30 days after ERCOT approves the restock of the burned fuel as described in paragraph (5) of Section 3.14.5, Firm Fuel Supply Service; or the Fuel Oil Index Price (FOP) for the Operating Day the QSE received approval to restock fuel, which includes $0.05/gallon to cover the cost of transportation.
Action Log 6 milestones
Amendments
DateBodyMotionResult
Dec 12 '24PRS To recommend approval of NPRR1251 as amended by the 12/5/24 WMS commentsPassed
Ballots
DateBodyResultYesNoAbstain
Jan 22 '25 TAC Motion Passes 28 0 0 xls
Jan 15 '25 PRS Motion Carries 7 0 1 xls
Dec 12 '24 PRS Motion Carries 6 0 1 xls
Dec 4 '24 WMS Motion Carries 7.5 0 0 xls
Oct 7 '24 WMS Motion Carries 7.5 0 0 xls
Sep 12 '24 PRS Motion Carries 7 0 0 xls
Documents 16
NameTypePostedClassification
1251NPRR-01 Updated FFSS Fuel Replacement Costs Recovery Process 082824 docx Aug 28 '24 Revision Request
1251NPRR-02 Impact Analysis 082824 docx Aug 28 '24 Staff Report
1251NPRR-03 PRS Ballot 091224 xls Sep 16 '24 Revision Request Ballot
1251NPRR-04 PRS Report 091224 docx Sep 16 '24 Committee Report
1251NPRR-05 WMS Ballot 100724 xls Oct 8 '24 Revision Request Ballot
1251NPRR-06 WMS Comments 100824 docx Oct 8 '24 Revision Request Comments
1251NPRR-07 WMS Ballot 120424 xls Dec 5 '24 Revision Request Ballot
1251NPRR-08 WMS Comments 120524 docx Dec 5 '24 Revision Request Comments
1251NPRR-09 PRS Ballot 121224 xls Dec 16 '24 Revision Request Ballot
1251NPRR-10 PRS Report 121224 docx Dec 16 '24 Committee Report
1251NPRR-11 PRS Ballot 011525 xls Jan 16 '25 Revision Request Ballot
1251NPRR-12 PRS Report 011525 docx Jan 16 '25 Committee Report
1251NPRR-13 TAC Ballot 012225 xls Jan 23 '25 Revision Request Ballot
1251NPRR-14 TAC Report 012225 docx Jan 23 '25 Committee Report
1251NPRR-15 Board Report 020425 docx Feb 6 '25 Committee Report
1251NPRR-16 PUCT Report 031325 docx Mar 17 '25 Committee Report
Meetings That Took It Up 11
DateMeetingCommitteeStatus
Feb 4 '25 Board of Directors Meeting BOARD Concluded
Jan 22 '25 TAC Meeting - Webex Only TAC Concluded
Jan 15 '25 PRS Meeting PRS Concluded
Dec 12 '24 PRS Meeting PRS Concluded
Dec 4 '24 WMS Meeting WMS Concluded
Nov 15 '24 RCWG Meeting - Webex Only RCWG Concluded
Nov 14 '24 PRS Meeting PRS Concluded
Nov 6 '24 WMS Meeting WMS Concluded
Oct 17 '24 PRS Meeting PRS Concluded
Oct 7 '24 WMS Meeting - Webex Only WMS Concluded
Sep 12 '24 PRS Meeting PRS Concluded