NPRR #1244 · Revision Request
NPRR1244 Clarification of Controllable Load Resource Primary Frequency Response Responsibilities
ReasonGeneral system and/or process improvement(s)
Created2024-08-08
Approved2024-11-21
Sections Affected
3.6.16.5.7.58.5.2.1
Summary
This Nodal Protocol Revision Request (NPRR) aligns provisions regarding eligibility of a Controllable Load Resource that is not providing Primary Frequency Response (“PFR”) to provide ERCOT Contingency Reserve Service (ECRS), and the calculation of Physical Responsive Capability (PRC) to include only the capacity of Controllable Load Resources when they are qualified to provide Regulation Service and/or Responsive Reserve (RRS) which requires the Controllable Load Resource to be capable of providing PFR.
Action Log 5 milestones
-
Aug 8
PRSRecommended for Approval→ Impact Analysis Consideration
-
Sep 12
PRSRecommended for Approval→ Revision Request Consideration
-
Sep 19
TACRecommended for Approval→ Revision Request Consideration
-
Oct 10
BOARDRecommended for Approval→ Revision Request Consideration
-
Nov 21
PUCTApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Sep 12 '24 | PRS | to endorse and forward to TAC the 8/8/24 PRS Report as revised by PRS and 9/6/24 Impact Analysis for NPRR1244 with a recommended priority of 2025 and rank of 4530 | Passed |
| Sep 19 '24 | TAC | to recommend approval of NPRR1244 as recommended by PRS in the 9/12/24 PRS Report; and the 9/13/24 Revised Impact Analysis; with a recommended priority of 2026 and rank of 4710 | Passed |
Ballots
| Date | Body | Result | Yes | No | Abstain | |
|---|---|---|---|---|---|---|
| Sep 19 '24 | TAC | Motion Passes | 29 | 0 | 0 | xls |
| Sep 12 '24 | PRS | Motion Carries | 7 | 0 | 0 | xls |
| Aug 8 '24 | PRS | Motion Carries | 7 | 0 | 0 | xls |
Documents 11
| Name | Type | Posted | Classification |
|---|---|---|---|
| 1244NPRR-01 Related to NOGRR263, Clarification of Controllable Load Resource Primary Frequency Response Responsibilities 072424 | docx | Jul 24 '24 | Revision Request |
| 1244NPRR-02 PRS Ballot 080824 | xls | Aug 12 '24 | Revision Request Ballot |
| 1244NPRR-03 PRS Report 080824 | docx | Aug 12 '24 | Committee Report |
| 1244NPRR-04 Impact Analysis 090624 | docx | Sep 6 '24 | Staff Report |
| 1244NPRR-05 PRS Ballot 091224 | xls | Sep 13 '24 | Revision Request Ballot |
| 1244NPRR-06 PRS Report 091224 | docx | Sep 19 '24 | Committee Report |
| 1244NPRR-07 Revised Impact Analysis 091324 | docx | Sep 13 '24 | Staff Report |
| 1244NPRR-08 TAC Ballot 091924 | xls | Sep 24 '24 | Revision Request Ballot |
| 1244NPRR-09 TAC Report 091924 | docx | Sep 24 '24 | Committee Report |
| 1244NPRR-10 Board Report 101024 | docx | Oct 14 '24 | Committee Report |
| 1244NPRR-11 PUCT Report 112124 | docx | Nov 26 '24 | Committee Report |
Meetings That Took It Up 4
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Oct 10 '24 | Board of Directors Meeting | BOARD | Concluded |
| Sep 19 '24 | TAC Meeting | TAC | Concluded |
| Sep 12 '24 | PRS Meeting | PRS | Concluded |
| Aug 8 '24 | PRS Meeting | PRS | Concluded |