NPRR #1220 · Revision Request
NPRR1220 Market Restart Approval Process Modifications
- PRS May 9 '24
- TAC May 22 '24
- BOARD Jun 18 '24
- PUCT Jul 25 '24
ReasonGeneral system and/or process improvement(s)
Created2024-04-05
Approved2024-07-25
Sections Affected
25.3
Summary
This Nodal Protocol Revision Request (NPRR) modifies the Market Restart process. The proposed process requires Technical Advisory Committee (TAC) and ERCOT Board approval, with an alternative mechanism to ERCOT Board approval where circumstances require it.
Timeline
- Mar 20
-
Apr 5
PRS PRS Meeting - Webex OnlyPRSRecommended for Approval“to recommend approval of NPRR1220 as submitted” — Passed→ Impact Analysis Consideration
-
May 9
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“to endorse and forward to TAC the 4/5/24 PRS Report and 3/20/24 Impact Analysis for NPRR1220” — Passed→ Revision Request Consideration
-
May 22
TAC TAC MeetingTACRecommended for Approval“to recommend approval of NPRR1220 as recommended by PRS in the 5/9/24 PRS Report” — Passed→ Revision Request Consideration
-
Jun 18
BOARD Board of Directors MeetingBOARDRecommended for Approval“to recommend approval of NPRR1220 as recommended by TAC in the 5/22/24 TAC Report” — Passed→ Revision Request Consideration
-
Jul 25
PUCTPUCTApproved“to approve NPRR1220 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
-
—