NPRR #1202 · Revision Request
NPRR1202 Refundable Deposits for Large Load Interconnection Studies
- PRS withdrawn Nov 9 '23
- TAC —
- BOARD —
- PUCT —
ReasonStrategic Plan Objective 1
Created2023-10-12
Sections Affected
2.13.24 (new)and ERCOT Fee Schedule
Summary
This Nodal Protocol Revision Request (NPRR) directs ERCOT to charge refundable deposits to Entities that request a Large Load Interconnection Study (LLIS).
Timeline
- Sep 22
- Oct 12
- Oct 23
-
Nov 9
PRS PRS MeetingPRSDeferred/Tabled Referred → WMS“To table NPRR1202 and refer the issue to WMS” — Passed→ PRS for consideration
- Dec 6
- Dec 15
-
Jan 10
Listed without action at 18 meetings (Jan 10 '24 – Sep 12 '24)
- Oct 7
- Oct 17
-
Oct 18
Listed without action at 1 meeting
- Nov 6
-
Nov 14
Listed without action at 2 meetings (Nov 14 '24 – Dec 4 '24)
- Dec 12
-
Jan 8
Listed without action at 2 meetings (Jan 8 '25 – Jan 15 '25)
-
Feb 5
WMS WMS Meeting“To advise PRS that WMS has concluded discussion of NPRR1202 and has no recommendation at this time”
- Feb 12
-
Mar 4
Listed without action at 4 meetings (Mar 4 '25 – May 14 '25)
- Jun 11