NPRR #1197 · Revision Request
NPRR1197 Optional Exclusion of Load from Netting at ERCOT-Polled Settlement (EPS) Metering Facilities which Include Resources
- PRS Mar 20 '24
- TAC Mar 27 '24
- BOARD Apr 23 '24
- PUCT Jun 13 '24
ReasonGeneral system and/or process improvement(s)
Created2023-10-12
Approved2024-06-13
Sections Affected
10.3.2.3 and 11.1.6
Summary
This Nodal Protocol Revision Request (NPRR) adds the ability for Resources to separately meter and settle Load(s) located behind the EPS metering point at the Resource’s POI.
Timeline
- Aug 31
- Sep 13
- Oct 11
-
Oct 12
PRS PRS MeetingPRSDeferred/Tabled Referred → WMS“To table NPRR1197 and refer the issue to WMS” — Passed→ PRS for consideration
- Nov 1
-
Nov 8
Listed without action at 5 meetings (Nov 8 '23 – Dec 15 '23)
- Jan 10
-
Jan 11
Listed without action at 1 meeting
-
Feb 8
PRS PRS MeetingPRSRecommended for Approval Amended by the Feb 7 '24 Oncor comments“To recommend approval of NPRR1197 as amended by the 2/7/24 Oncor comments as revised by PRS” — Passed→ PRS for Impact Analysis consideration
-
Mar 20
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward to TAC the 2/8/24 PRS Report and 2/28/24 Impact Analysis for NPRR1197” — Passed→ TAC for consideration
-
Mar 27
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR1197 as recommended by PRS in the 3/20/24 PRS Report” — Passed→ Board for consideration
- Apr 22
-
Apr 23
BOARD Board of Directors MeetingBOARDRecommended for Approval“To recommend approval of NPRR1197 as recommended by TAC in the 3/27/24 TAC Report” — Passed→ PUCT for consideration
-
Jun 13
PUCTPUCTApproved“To approve NPRR1197 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
- Sep 12
-
Oct 17
Listed without action at 3 meetings (Oct 17 '24 – Dec 3 '24)