NPRR #1193 · Revision Request
NPRR1193 Related to SMOGRR027, Move OBD to Settlement Metering Operating Guide – EPS Metering Design Proposal
- PRS Oct 12 '23
- TAC Feb 14 '24
- BOARD Feb 27 '24
- PUCT Apr 11 '24
ReasonGeneral system and/or process improvement(s)
Created2023-09-13
Approved2024-04-11
Sections Affected
10.4.2
Summary
This Nodal Protocol Revision Request (NPRR) changes the referenced location of the EPS Design Proposal Form, as it is moving from the Other Binding Document List into the Settlement Metering Operating Guide (SMOG).
Timeline
- Aug 9
-
Sep 13
PRS PRS MeetingPRSRecommended for Approval“to recommend approval of NPRR1193 as submitted” — Passed→ Impact Analysis Consideration
-
Oct 12
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“to endorse and forward to TAC the 9/13/23 PRS Report and 8/9/23 Impact Analysis for NPRR1193” — Passed→ Revision Request Consideration
- Oct 24
- Nov 8
-
Dec 4
Listed without action at 2 meetings (Dec 4 '23 – Jan 24 '24)
-
Feb 14
TAC TAC MeetingTACRecommended for Approval“to recommend approval of NPRR1193 as recommended by PRS in the 10/12/23 PRS Report” — Passed→ Revision Request Consideration
-
Feb 27
BOARD Board of Directors MeetingBOARDRecommended for Approval“to recommend approval of NPRR1193 as recommended by TAC in the 2/14/24 TAC Report” — Passed→ Revision Request Consideration
-
Apr 11
PUCTPUCTApproved“to approve NPRR1193 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
-
—
Posted since the last meeting