NPRR #1192 · Revision Request

NPRR1192  Move OBD to Section 22 – Requirements for Aggregate Load Resource Participation in the ERCOT Markets

Approved sponsor ERCOT posted 2023-08-08 ercot.com
ReasonAdministrative
Created2023-09-13
Approved2024-02-01
Sections Affected
6.5.7.6.2.38.1.1.210.9and 22 Attachment O (new)
Summary
This Nodal Protocol Revision Request (NPRR) incorporates the Other Binding Document “Requirements for Aggregate Load Resource Participation in the ERCOT Markets” into the Protocols.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Sep 13 '23PRS to recommend approval of NPRR1192 as revised by PRSPassed
Oct 12 '23PRS to endorse and forward to TAC the 9/13/23 PRS Report and 9/12/23 Revised Impact Analysis for NPRR1192Passed
Ballots
DateBodyResultYesNoAbstain
Oct 24 '23 TAC Motion Passes 30 0 0 xls
Oct 12 '23 PRS Motion Carries 7 0 0 xls
Sep 13 '23 PRS Motion Carries 6 0 0 xls
Documents 11
NameTypePostedClassification
1192NPRR-01 Move OBD to Section 22 – Requirements for Aggregate Load Resource Participation in the ERCOT Markets 080823 doc Aug 8 '23 Revision Request
1192NPRR-02 Impact Analysis 080823 docx Aug 8 '23 Staff Report
1192NPRR-03 Revised Impact Analysis 091223 docx Sep 12 '23 Staff Report
1192NPRR-04 PRS Ballot 091323 xls Sep 18 '23 Revision Request Ballot
1192NPRR-05 PRS Report 091323 docx Sep 18 '23 Committee Report
1192NPRR-06 PRS Ballot 101223 xls Oct 16 '23 Revision Request Ballot
1192NPRR-07 PRS Report 101223 docx Oct 16 '23 Committee Report
1192NPRR-08 TAC Ballot 102423 xls Oct 27 '23 Revision Request Ballot
1192NPRR-09 TAC Report 102423 docx Oct 27 '23 Committee Report
1192NPRR-10 Board Report 121923 docx Dec 21 '23 Committee Report
1192NPRR-11 PUCT Report 020124 docx Feb 5 '24 Committee Report
Meetings That Took It Up 4
DateMeetingCommitteeStatus
Dec 19 '23 Board of Directors Meeting BOARD Concluded
Oct 24 '23 TAC Meeting TAC Concluded
Oct 12 '23 PRS Meeting PRS Concluded
Sep 13 '23 PRS Meeting PRS Concluded