NPRR #1164 · Revision Request
NPRR1164 Black Start and Isochronous Control Capable Identification
- PRS Aug 10 '23
- TAC Aug 22 '23
- BOARD Aug 31 '23
- PUCT Oct 12 '23
ReasonOther
Created2023-03-08
Approved2023-10-12
Sections Affected
2.13.10.7.1.3and 3.14.2
Summary
This Nodal Protocol Revision Request (NPRR) requires that Resource Entities identify whether a physical Resource has the potential capability (even if unverified) to be called upon or used during a black start emergency or if it has the capability for isochronous control, and requires that Resource Entities and Transmission Service Providers (TSPs) identify if a breaker or switch has a Synchroscope or Synchronism Check Relay. This Revision Request defines the terms Black Start Capable Resource, Isochronous Control Capable Resource, Synchroscope, and Synchronism Check Relay.
Timeline
- Feb 21
-
Mar 8
PRS PRS MeetingPRSDeferred/Tabled Referred → ROS“to table NPRR1164 and refer the issue to ROS” — Passed→ Impact Analysis Consideration
-
Apr 4
Listed without action at 1 meeting
-
Apr 6
ROS ROS Meeting“To request PRS continue to table NPRR1164 for further review by the NDSWG and SPWG”
- Apr 13
-
May 4
Listed without action at 4 meetings (May 4 '23 – Jun 14 '23)
- Jul 6
-
Jul 13
PRS PRS MeetingPRSRecommended for Approval“to recommend approval of NPRR1164 as submitted” — Passed→ Impact Analysis Consideration
- Aug 3
-
Aug 10
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC priority 2023 · rank 3810“to endorse and forward to TAC the 7/13/23 PRS Report and 2/21/23 Impact Analysis for NPRR1164 with a recommended priority of 2023 and rank of 3810” — Passed→ Revision Request Consideration
-
Aug 22
TAC TAC Meeting - Webex OnlyTACRecommended for Approval Amended by the Aug 10 '23 TAC comments“to recommend approval of NPRR1164 as recommended by PRS in the 8/10/23 PRS Report as revised by TAC” — Passed→ Revision Request Consideration
-
Aug 31
BOARD Board of Directors MeetingBOARDRecommended for Approval“to recommend approval of NPRR1164 as recommended by TAC in the 8/22/23 TAC Report” — Passed→ Revision Request Consideration
-
Oct 12
PUCTPUCTApproved“to approve NPRR1164 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Rules Adopted by the Independent Organization” — Passed
-
—
Posted since the last meeting