NPRR #1161 · Revision Request

NPRR1161  Clarify AVR Notification Requirements for IRRs

Approved sponsor ERCOT posted 2023-02-07 ercot.com
ReasonAddresses current operational issues
Created2023-03-08
Approved2023-07-20
Sections Affected
6.5.5.1
Summary
This Nodal Protocol Revision Request (NPRR) clarifies that Intermittent Renewable Resources (IRRs), who remain synchronized to the ERCOT System but are not able to provide reactive power when not providing real power, do not have to notify ERCOT other than the Real-Time telemetered status.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Apr 13 '23PRS to endorse and forward to TAC the 3/8/23 PRS Report as revised by PRS and the 2/7/23 Impact Analysis for NPRR1161Passed
Ballots
DateBodyResultYesNoAbstain
May 23 '23 TAC 28 0 1 xls
Apr 13 '23 PRS Motion Carries 7 0 0 xls
Mar 8 '23 PRS Motion Carries 7 0 0 xls
Documents 10
NameTypePostedClassification
1161NPRR-01 Clarify AVR Notification Requirements for IRRs 020723 docx Feb 7 '23 Revision Request
1161NPRR-02 Impact Analysis 020723 docx Feb 7 '23 Staff Report
1161NPRR-03 PRS Ballot 030823 xls Mar 9 '23 Revision Request Ballot
1161NPRR-04 PRS Report 030823 docx Mar 9 '23 Committee Report
1161NPRR-05 PRS Ballot 041323 xls Apr 13 '23 Revision Request Ballot
1161NPRR-06 PRS Report 041323 docx Apr 13 '23 Committee Report
1161NPRR-07 TAC Ballot 052323 xls May 25 '23 Revision Request Ballot
1161NPRR-08 TAC Report 052323 docx May 25 '23 Committee Report
1161NPRR-09 Board Report 062023 docx Jun 21 '23 Committee Report
1161NPRR-10 PUCT Report 072023 docx Jul 20 '23 Committee Report
Meetings That Took It Up 7
DateMeetingCommitteeStatus
Jun 20 '23 Board of Directors Meeting BOARD Concluded
May 23 '23 TAC Meeting - Webex Only TAC Concluded
Apr 13 '23 PRS Meeting PRS Concluded
Apr 6 '23 ROS Meeting ROS Concluded
Mar 14 '23 MCWG Meeting - Webex Only MCWG Concluded
Mar 8 '23 PRS Meeting PRS Concluded
Mar 2 '23 ROS Meeting ROS Concluded