NPRR #1139 · Revision Request
NPRR1139 Adjustments to Capacity Shortfall Ratio Share for IRRs
ReasonAddresses current operational issues / Market efficiencies or enhancements
Created2022-06-09
Approved2022-11-03
Sections Affected
5.7.4.1 and 5.7.4.1.1
Summary
This Nodal Protocol Revision Request (NPRR) replaces the usage of the Wind-powered Generation Resource Production Potential (WGRPP) and PhotoVoltaic Generation Resource Production Potential (PVGRPP) with the High Sustained Limit (HSL) of an Intermittent Renewable Resource (IRR) as reflected in the Current Operating Plan (COP), similar to treatment afforded to Resources that are not IRRs. This NPRR also makes a minor adjustment in Section 5.7.4.1, changing the name of a variable in a formula from HSL to RUCHSL in order to match the variable name in the Protocols to the data value available in the Settlement extracts.
Action Log 6 milestones
-
Jun 9
PRSDeferred/Tabled→ PRS for consideration
-
Aug 11
PRSRecommended for Approval→ PRS for Impact Analysis consideration
-
Sep 15
PRSRecommended for Approval→ TAC for consideration
-
Sep 28
TACRecommended for Approval→ Board for consideration
-
Oct 18
BOARDRecommended for Approval→ PUCT for consideration
-
Nov 3
PUCTApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Aug 11 '22 | PRS | To recommend approval of NPRR1139 as amended by the 7/29/22 ERCOT comments | Passed |
| Sep 15 '22 | PRS | To endorse and forward to TAC the 8/11/22 PRS Report and 8/23/22 Revised Impact Analysis for NPRR1139 with a recommended priority of 2023 and rank of 3740 | Passed |
Ballots
| Date | Body | Result | Yes | No | Abstain | |
|---|---|---|---|---|---|---|
| Sep 15 '22 | PRS | Motion Carries | 7 | 0 | 0 | xls |
| Aug 11 '22 | PRS | Motion Carries | 7 | 0 | 0 | xls |
| Aug 3 '22 | WMS | Motion Carries | 7.5 | 0 | 2 | xls |
| Jun 9 '22 | PRS | Motion Carries | 7 | 0 | 0 | xls |
Documents 16
| Name | Type | Posted | Classification |
|---|---|---|---|
| 1139NPRR-01 Adjustments to Capacity Shortfall Ratio Share for IRRs 052522 | docx | May 25 '22 | Revision Request |
| 1139NPRR-02 Impact Analysis 052522 | docx | May 25 '22 | Staff Report |
| 1139NPRR-03 PRS Ballot 060922 | xls | Jun 13 '22 | Revision Request Ballot |
| 1139NPRR-04 PRS Report 060922 | docx | Jun 13 '22 | Committee Report |
| 1139NPRR-05 ERCOT Comments 072922 | docx | Jul 29 '22 | Revision Request Comments |
| 1139NPRR-06 WMS Ballot 080322 | xls | Aug 5 '22 | Revision Request Ballot |
| 1139NPRR-07 WMS Comments 080522 | doc | Aug 5 '22 | Revision Request Comments |
| 1139NPRR-08 PRS Ballot 081122 | xls | Aug 16 '22 | Revision Request Ballot |
| 1139NPRR-09 PRS Report 081122 | docx | Aug 16 '22 | Committee Report |
| 1139NPRR-10 Revised Impact Analysis 082322 | docx | Aug 23 '22 | Staff Report |
| 1139NPRR-11 PRS Ballot 091522 | xls | Sep 19 '22 | Revision Request Ballot |
| 1139NPRR-12 PRS Report 091522 | docx | Sep 19 '22 | Committee Report |
| 1139NPRR-13 TAC Ballot 092822 | xls | Sep 29 '22 | Revision Request Ballot |
| 1139NPRR-14 TAC Report 092822 | docx | Sep 29 '22 | Committee Report |
| 1139NPRR-15 Board Report 101822 | docx | Oct 19 '22 | Committee Report |
| 1139NPRR-16 PUCT Report 110322 | docx | Nov 3 '22 | Committee Report |
Meetings That Took It Up 8
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Oct 18 '22 | Board of Directors Meeting | BOARD | Concluded |
| Sep 28 '22 | TAC Meeting | TAC | Concluded |
| Sep 15 '22 | PRS Meeting | PRS | Concluded |
| Aug 11 '22 | PRS Meeting | PRS | Concluded |
| Aug 3 '22 | WMS Meeting | WMS | Concluded |
| Jul 26 '22 | WMWG Meeting by Webex Only | WMWG | Concluded |
| Jul 13 '22 | PRS Meeting | PRS | Concluded |
| Jun 9 '22 | PRS Meeting | PRS | Concluded |